在西气东输二线Φ1219mm×22mm水平定向钻穿越工程中,国内首次采用聚乙烯管(简称PE管)作为配重管的施工方式,应用在大口径、长距离、复杂岩石地层穿越中。选择合适管径的PE管,充水后安装在回拖管道中,保证了回拖管在回拖过程中悬浮于孔洞中,减小了管道与岩石孔洞的摩擦及防腐层损伤,且降低了回拖时管道卡阻风险。现以西二线工程中潦河定向钻穿越为例,探讨了PE配重管在水平定向钻穿越施工中的应用。
In the Φ1219mm × 22mm horizontal directional drilling crossing project of the second West-East Gas Pipeline project, the first polyethylene pipe (PE pipe) in China is used as the construction method of the counterweight pipe, which is used in the crossing of large-caliber, long-distance and complex rock strata. Select the PE pipe with the proper pipe diameter and install it in the dragging pipe after water filling to ensure that the drag pipe is suspended in the hole during the dragging process so as to reduce the friction between the pipe and the rock hole and the damage of the coating and reduce the Back to the pipe when the drag blocking the risk. Now the second-line project in the Liao River directional drilling through an example, discussed the application of PE pipe in the horizontal directional drilling through construction.