云峰发电厂位于鸭绿江中游的吉林省集安市境内,隶属国家电网公司东北电网有限公司,是中朝两国共同投资修建并由中方管理的大型水力发电厂,是鸭绿江界河四座梯级电站中的第一级,主要担负调峰、调频任务。云峰电站主体工程于1959年9月开工,1965年9月9日第1台机组投产发电,电站装机总容量40万千瓦,单机容量10万千瓦。四台机组中,
Yunfeng Power Plant is located in Ji’an City, Jilin Province, in the middle reaches of the Yalu River and is part of the State Grid Corporation Northeast Power Grid Co., Ltd. It is a large-scale hydropower plant jointly built and managed by China and North Korea and managed by the Chinese government. It is a member of the cascade hydropower station at the Yalu River boundary. The first level is mainly responsible for the tasks of peak shaving and frequency modulation. The main project of Yunfeng Power Station commenced in September 1959 and the first unit was put into operation on September 9, 1965. The total installed capacity of the power station was 400,000 kilowatts and the stand-alone capacity was 100,000 kilowatts. In the four units,