在运营的铁路线上,有一些是解放前修建的桥梁。由于当时水文计算不准确或因盲目降低造价,致使一些桥梁发生水淹钢梁或冲断路基等水害。在历年的桥梁大修工程中先后修复了一批桥梁,但还有一部分尚未解决。我队这次在京广线白水桥在不中断运输、不修便线的条件下,抬梁抬道1.2米,解决了水害问题。现将施工方法简介如下。
On the railway line operated, some are bridges built before the liberation. Due to inaccurate hydrological calculations or blindly reducing the cost at that time, some bridges suffered water damage such as steel beams or thrust subgrade. In the bridge overhaul project over the years has repaired a number of bridges, but there are still some unsolved. My team in the Beijing-Guangzhou line Baishui Bridge without interruption in the transport, do not repair the line conditions, lift the beam lift road 1.2 meters, to solve the problem of water damage. Now the construction method is as follows.