摘要:质量就是生命,在变电站土建施工项目管理中,我们要站在企业生存与发展的高度来认识施工质量的重大意义,坚持“以质取胜”的经营战略,科学管理、规范施工,提高变电站土建工程的质量。良好的工程质量是在施工过程中一步一步做出来的,而不是靠最后检验出来的。为了把好工程质量,应该从带有误导性的事后检查把关转向事前控制,真正做到“预防为主”的目的,分析找出每道工序常见的问题,研究对策,提出处理办法,提高每道施工工序的质量控制。
关键词:变电站,土建施工,质量控制
Abstract: quality is life, in substation construction project management, we must stand in the enterprise survival and the development height to realize the significance of the construction quality, adhere to the "quality win" business strategy, scientific management, the standard construction, improve the quality of civil engineering transformer substation. Good engineering quality is in construction process to make step by step, and not on the final test it out. In order to put the good engineering quality, should with misleading afterward inspections from control to beforehand control, accomplish truly "prevention first" purpose, analysis to discover each procedure common problems, countermeasures study and propose treatment method, improve the quality of each construction process control.
Keywords: substations, civil construction, quality control
中图分类号: TV523文献标识码:A文章编号:
1.变电站土建施工原则
1.1严格控制质量,提高进度
本着创造优质工程的目标,在进行工程建设的时候,严格执行质量体系程序文件中的有关程序及国家规定的施工要求。对关键部分、薄弱的环节、施工技术以及安装的工艺技术、质量的攻关与工艺改进活动等,发动施工管理人员、班组负责人、技术骨干积极参与,共同探讨总结,采用科学的、严格的管理办法和措施。对施工的技术要求、施工方案、质量标准等加以详细说明,使施工人员心中有数;同类工作大范围施工前,工程技术人员应与施工人员一道,设置施工工艺样板,以样板作为参照,指导工人施工及现场对比纠正。坚持三级检查规则,设置质量跟踪卡,上道工序未经检查合格前,坚决不能进行下一道工序施工;定期的向工程法人和监理工程师汇报工程质量情况;配合法人与监理工程师的检查、验收工作,同时,提供必须的检查条件及检测手段。
1.2严格对流程的控制,细化措施
变电站工程,特别是运行站,所有项目的共同特点是风险指数极高,危险源很多。小小的失误有可能造成电源点至电网或者用户的一系列事故。所以,电力行业的安全施工必须严格要求,现场要布置的井井有条,材料应该分区堆放,各类安全标识要齐全;各层工作人员要统一着装,依据规定佩带各自的安全帽;每周进行安全教育,每天都要坚持班前的安全会;组织工人的进行安全学习考试,设置奖励措施,对成绩优异者给予物质等奖励。
2变电站土建工程施工的特点
2.1资金投入大,技术含量高。变电站土建施工与普通的土建施工相比,其精密程度和涉及到的设备以及综合自动化程度更高,很多项目都有着专业的施工技术要求。
2.2地质、地形条件限制较大。新建变电站的选址一般都是根据整个供电系统的需要,变电站站址的选择是根据系统的需要,选择供电网络的某个区域建设,在网络的某个区域布点。因为这样的布点,很容易出现地形和地质条件复杂的情况,造成变电站的土建施工建设难度提升。
2.3变电站土建施工一般占地面积较大,站内都有种类繁多的建(构)筑物,这些建筑物结构独立又互相关联,根据变电站的电压等级、设备布置方式以及出线规模的不同,土建施工的任務也有很大的区别。
2.4变电站土建工程质量主要由可行性研究、初步设计、施工设计等阶段的工作决定的,变电站土建施工的特殊性决定了要想保证施工的质量,必须由多方共同协调参与,才能保证。
2.5参与变电站土建施工的单位较多,包括业主、设计单位、施工企业、设备供货商、监理方以及调试单位,监理方的主要工作是土建施工现场协调及监督。
3施工准备阶段
3.1组织机构:要提高工程的质量,人是第一要素,必须要有一个懂业务、强有力的项目部,选好项目经理是首要的,项目经理不但要懂管理、懂技术、更要责任心强。要有一批熟练各专业的管理人员和技术工人。这些是保证土建工程质量的首要条件。
3.2技术准备:重视施工图纸的会审质量。项目部的各人员要认真仔细的审阅施工图纸,记录好施工图纸中的问题。特别要注意土建与各专业的配合衔接。水电、通讯、通风、消防、监控系统等施工都会提前在土建施工阶段实施预埋管线或预留孔,尽量避免相互不协调,事后打凿墙体。在图纸会审中认真听取设计单位人员对施工图技术交底以及回答施工图中的问题。
工程开工前,由项目总工或技术负责人组织对整个变电站土建工程进行全面的技术交底。各分项工程施工前,由项目技术负责人向参加该项目施工的所有施工队班组和配合工种进行技术交底。交底的内容包括图纸交底、施工组织设计交底、分项工程技术交底和安全交底等。通过交底明确变电站工程的基本情况,总体的布置,有几个电压等级,各个电压等级有几个间隔。各个间隔设备基础轴线、尺寸、标高、预留孔洞、预埋件、材料规格及混凝土配合比等技术要求,明确工序搭接、工种配合,施工方法、进度等施工安排。明确对质量、安全采取的措施和要求。
3.3工器具准备:大量采用先进的、合适的工器具、施工机械及检测工具,对控制施工质量、加快施工进度都有很大的帮助。工程施工人员在工程开工前应积极进行工器具的选型,淘汰旧的工器具及施工机械、检测工具,确定具体的施工方案及工艺做法。
4变电站中主控制楼存在的问题及预防措施
4.1土方及基坑工程:重点检查是否开挖到了持力层,是否存在边坡塌方问题。预防措施是:根据地质报告估测持力层的深度,对基底进行扦探,防止把场地平整时的压实填土当作原状土,严格执行地基验槽、基础隐蔽工程的验收程序。严格按设计要求和根据土质情况按现行的施工规范要求放坡,严禁在基坑边堆土和存放材料,避免车辆和机械设备的振动。
4.2地基及基础处理工程:需注意的是浇筑基础混凝土时基坑是否有积水,水泡的软弱层是否清理完毕。由于我们地处南方,雨水多,雨季施工基础必须清干基础的积水,清理完水泡软的土层,方可施工。基础混凝土基础施工完毕,要尽快对基础进行回填,严防不及时回填基础导致雨水积在已浇筑了混凝土的基坑槽内,如长期积水下渗,会影响地基承载力。我们常采用的地基处理方法人工挖孔桩必需注意施工安全问题,做好通风和防吊桶坠落,需要配足完好的鼓风机和抽水机,开工前十分钟和施工过程中必须对孔桩内进行抽水鼓风。吊桶的吊绳和桶钩每天进行检查,绞轮必须有防飞车装置。在孔桩的质量方面注意钢筋笼是否变形,保护层不够等问题。这方面的预防措施是:钢筋笼采用分段制作,吊入孔时再分段焊接,钢筋笼设置加强箍筋,防止在搬运和吊装中变形,在钢筋笼周围放置一些混凝土垫块,混凝土垫块的厚度要根据保护层来设定。
4.3砌体工程:砌体工程控制的问题是,砖缝砂浆不饱满,特别是竖缝,砂浆不饱满比较普遍,砂浆与砖不粘结不好,灰缝过厚,墙体留搓不设置拉结钢筋,预埋管线、预留孔洞、预埋件等漏缺。预防措施是:加强对砌砖人员的培训,规范操作,砌筑烧结砖和多孔砖时需提前一天淋水,砖要湿透晾干,砌墙前先测所砌部位的墙面标高,要设置皮数杆,所购买的砖外形尺寸要符合要求,每几皮砖通一次线,及时发现标高偏差,灰缝误差。对预留槎口要统一规划考虑,不要随意留槎口,要按规定设置拉结钢筋。填充墙砌至梁底板底时,要留一定的空隙,填充墙砌筑完毕15d以后,才可将其补砌,补砌需挤紧,补砌时,双侧竖缝用高标号水泥浆嵌填密实。加强各专业协调配合,专人检查预埋管线,预埋件的安放,预留孔洞的预留。
4.4混凝土工程:需重点控制的混凝土蜂窝麻面,梁、柱、墙胀肚起鼓,钢筋搭接绑扎质量。预防措施是模板及支撑系统必需设计好,牢固可靠成一整体,禁止模板支撑和脚手架同为一个系统,模板及支撑要有足够的刚度和稳定性,梁、柱的龙骨的截面要足够大,龙骨间距根据梁柱截面定,一般控制在50cm內,卡具要足够。混凝土要按配合比下料,控制好塌落度,浇筑时要均匀下料,严格控制浇灌高度,加强对振捣人员的培训,控制振捣时间和方法,防止漏振又要防止过分振捣引起模板变形。钢筋加工的绑扎要严格按图施工,钢筋的接头必需符合施工图纸及施工规范要求,钢筋绑扎完毕后,要认真做好验收工作,做好隐蔽工程记录。架空铺好混凝土运输的脚手架,严禁施工人员踩上绑扎验收好的钢筋。
4.5楼地面工程:注意的问题是地面下沉,地面施工前要清理干净垃圾、松土,特别是膨胀土,要进行换土处理,填土要分层夯实,控制好填土的含水量。预埋件、预埋孔洞、预埋管线等漏缺,标高及定位尺寸偏差大。
4.6抹灰工程:一般容易发生裂缝和空鼓的问题,采取的措施,抹灰前烧结砖墙要预先淋水湿润表面晾干,混凝土面要做喷浆处理,在不同材料的交接处,铺钉铁丝网,抹灰要分层进行,严禁一次抹成,严格控制每遍的厚度不超过要求,每层抹灰的间隔时间不宜过短,要得等前层达到7~8成干时方可进行下层抹灰,严格按照配合比的要求搅拌砂浆,控制好砂浆的稠度。抹平后控制好最后收浆的时间,消除因砂浆收缩而产生的裂缝。
4.7层面防水:问题是起鼓和渗漏,采取的控制办法是所选用的防水材料必须有出厂合格证或检验报告,现场取样送检各项性能指标应符合规范要求。卷材施工前,屋面基层或保温层表面必须清理干净,干燥,泛水、落水窗口、伸缩缝等的防水构造处理必须认真细致,符合要求。基层处理剂必须刷透,卷材才能与基层牢固粘结,卷材的纵横搭接要符合规范要求,接缝处应封闭严密。
5结语
提高电力土建工程施工质量,在不断探索管理的新思路,探寻更为科学、先进的管理措施与技术,是每个电力工程企业共同追求的目标。不断完善企业管理及技术标准,努力提高施工质量,在激烈竞争的电力建设市场中,使企业能更好地生存、发展、壮大。
注:文章内所有公式及图表请以PDF形式查看。
关键词:变电站,土建施工,质量控制
Abstract: quality is life, in substation construction project management, we must stand in the enterprise survival and the development height to realize the significance of the construction quality, adhere to the "quality win" business strategy, scientific management, the standard construction, improve the quality of civil engineering transformer substation. Good engineering quality is in construction process to make step by step, and not on the final test it out. In order to put the good engineering quality, should with misleading afterward inspections from control to beforehand control, accomplish truly "prevention first" purpose, analysis to discover each procedure common problems, countermeasures study and propose treatment method, improve the quality of each construction process control.
Keywords: substations, civil construction, quality control
中图分类号: TV523文献标识码:A文章编号:
1.变电站土建施工原则
1.1严格控制质量,提高进度
本着创造优质工程的目标,在进行工程建设的时候,严格执行质量体系程序文件中的有关程序及国家规定的施工要求。对关键部分、薄弱的环节、施工技术以及安装的工艺技术、质量的攻关与工艺改进活动等,发动施工管理人员、班组负责人、技术骨干积极参与,共同探讨总结,采用科学的、严格的管理办法和措施。对施工的技术要求、施工方案、质量标准等加以详细说明,使施工人员心中有数;同类工作大范围施工前,工程技术人员应与施工人员一道,设置施工工艺样板,以样板作为参照,指导工人施工及现场对比纠正。坚持三级检查规则,设置质量跟踪卡,上道工序未经检查合格前,坚决不能进行下一道工序施工;定期的向工程法人和监理工程师汇报工程质量情况;配合法人与监理工程师的检查、验收工作,同时,提供必须的检查条件及检测手段。
1.2严格对流程的控制,细化措施
变电站工程,特别是运行站,所有项目的共同特点是风险指数极高,危险源很多。小小的失误有可能造成电源点至电网或者用户的一系列事故。所以,电力行业的安全施工必须严格要求,现场要布置的井井有条,材料应该分区堆放,各类安全标识要齐全;各层工作人员要统一着装,依据规定佩带各自的安全帽;每周进行安全教育,每天都要坚持班前的安全会;组织工人的进行安全学习考试,设置奖励措施,对成绩优异者给予物质等奖励。
2变电站土建工程施工的特点
2.1资金投入大,技术含量高。变电站土建施工与普通的土建施工相比,其精密程度和涉及到的设备以及综合自动化程度更高,很多项目都有着专业的施工技术要求。
2.2地质、地形条件限制较大。新建变电站的选址一般都是根据整个供电系统的需要,变电站站址的选择是根据系统的需要,选择供电网络的某个区域建设,在网络的某个区域布点。因为这样的布点,很容易出现地形和地质条件复杂的情况,造成变电站的土建施工建设难度提升。
2.3变电站土建施工一般占地面积较大,站内都有种类繁多的建(构)筑物,这些建筑物结构独立又互相关联,根据变电站的电压等级、设备布置方式以及出线规模的不同,土建施工的任務也有很大的区别。
2.4变电站土建工程质量主要由可行性研究、初步设计、施工设计等阶段的工作决定的,变电站土建施工的特殊性决定了要想保证施工的质量,必须由多方共同协调参与,才能保证。
2.5参与变电站土建施工的单位较多,包括业主、设计单位、施工企业、设备供货商、监理方以及调试单位,监理方的主要工作是土建施工现场协调及监督。
3施工准备阶段
3.1组织机构:要提高工程的质量,人是第一要素,必须要有一个懂业务、强有力的项目部,选好项目经理是首要的,项目经理不但要懂管理、懂技术、更要责任心强。要有一批熟练各专业的管理人员和技术工人。这些是保证土建工程质量的首要条件。
3.2技术准备:重视施工图纸的会审质量。项目部的各人员要认真仔细的审阅施工图纸,记录好施工图纸中的问题。特别要注意土建与各专业的配合衔接。水电、通讯、通风、消防、监控系统等施工都会提前在土建施工阶段实施预埋管线或预留孔,尽量避免相互不协调,事后打凿墙体。在图纸会审中认真听取设计单位人员对施工图技术交底以及回答施工图中的问题。
工程开工前,由项目总工或技术负责人组织对整个变电站土建工程进行全面的技术交底。各分项工程施工前,由项目技术负责人向参加该项目施工的所有施工队班组和配合工种进行技术交底。交底的内容包括图纸交底、施工组织设计交底、分项工程技术交底和安全交底等。通过交底明确变电站工程的基本情况,总体的布置,有几个电压等级,各个电压等级有几个间隔。各个间隔设备基础轴线、尺寸、标高、预留孔洞、预埋件、材料规格及混凝土配合比等技术要求,明确工序搭接、工种配合,施工方法、进度等施工安排。明确对质量、安全采取的措施和要求。
3.3工器具准备:大量采用先进的、合适的工器具、施工机械及检测工具,对控制施工质量、加快施工进度都有很大的帮助。工程施工人员在工程开工前应积极进行工器具的选型,淘汰旧的工器具及施工机械、检测工具,确定具体的施工方案及工艺做法。
4变电站中主控制楼存在的问题及预防措施
4.1土方及基坑工程:重点检查是否开挖到了持力层,是否存在边坡塌方问题。预防措施是:根据地质报告估测持力层的深度,对基底进行扦探,防止把场地平整时的压实填土当作原状土,严格执行地基验槽、基础隐蔽工程的验收程序。严格按设计要求和根据土质情况按现行的施工规范要求放坡,严禁在基坑边堆土和存放材料,避免车辆和机械设备的振动。
4.2地基及基础处理工程:需注意的是浇筑基础混凝土时基坑是否有积水,水泡的软弱层是否清理完毕。由于我们地处南方,雨水多,雨季施工基础必须清干基础的积水,清理完水泡软的土层,方可施工。基础混凝土基础施工完毕,要尽快对基础进行回填,严防不及时回填基础导致雨水积在已浇筑了混凝土的基坑槽内,如长期积水下渗,会影响地基承载力。我们常采用的地基处理方法人工挖孔桩必需注意施工安全问题,做好通风和防吊桶坠落,需要配足完好的鼓风机和抽水机,开工前十分钟和施工过程中必须对孔桩内进行抽水鼓风。吊桶的吊绳和桶钩每天进行检查,绞轮必须有防飞车装置。在孔桩的质量方面注意钢筋笼是否变形,保护层不够等问题。这方面的预防措施是:钢筋笼采用分段制作,吊入孔时再分段焊接,钢筋笼设置加强箍筋,防止在搬运和吊装中变形,在钢筋笼周围放置一些混凝土垫块,混凝土垫块的厚度要根据保护层来设定。
4.3砌体工程:砌体工程控制的问题是,砖缝砂浆不饱满,特别是竖缝,砂浆不饱满比较普遍,砂浆与砖不粘结不好,灰缝过厚,墙体留搓不设置拉结钢筋,预埋管线、预留孔洞、预埋件等漏缺。预防措施是:加强对砌砖人员的培训,规范操作,砌筑烧结砖和多孔砖时需提前一天淋水,砖要湿透晾干,砌墙前先测所砌部位的墙面标高,要设置皮数杆,所购买的砖外形尺寸要符合要求,每几皮砖通一次线,及时发现标高偏差,灰缝误差。对预留槎口要统一规划考虑,不要随意留槎口,要按规定设置拉结钢筋。填充墙砌至梁底板底时,要留一定的空隙,填充墙砌筑完毕15d以后,才可将其补砌,补砌需挤紧,补砌时,双侧竖缝用高标号水泥浆嵌填密实。加强各专业协调配合,专人检查预埋管线,预埋件的安放,预留孔洞的预留。
4.4混凝土工程:需重点控制的混凝土蜂窝麻面,梁、柱、墙胀肚起鼓,钢筋搭接绑扎质量。预防措施是模板及支撑系统必需设计好,牢固可靠成一整体,禁止模板支撑和脚手架同为一个系统,模板及支撑要有足够的刚度和稳定性,梁、柱的龙骨的截面要足够大,龙骨间距根据梁柱截面定,一般控制在50cm內,卡具要足够。混凝土要按配合比下料,控制好塌落度,浇筑时要均匀下料,严格控制浇灌高度,加强对振捣人员的培训,控制振捣时间和方法,防止漏振又要防止过分振捣引起模板变形。钢筋加工的绑扎要严格按图施工,钢筋的接头必需符合施工图纸及施工规范要求,钢筋绑扎完毕后,要认真做好验收工作,做好隐蔽工程记录。架空铺好混凝土运输的脚手架,严禁施工人员踩上绑扎验收好的钢筋。
4.5楼地面工程:注意的问题是地面下沉,地面施工前要清理干净垃圾、松土,特别是膨胀土,要进行换土处理,填土要分层夯实,控制好填土的含水量。预埋件、预埋孔洞、预埋管线等漏缺,标高及定位尺寸偏差大。
4.6抹灰工程:一般容易发生裂缝和空鼓的问题,采取的措施,抹灰前烧结砖墙要预先淋水湿润表面晾干,混凝土面要做喷浆处理,在不同材料的交接处,铺钉铁丝网,抹灰要分层进行,严禁一次抹成,严格控制每遍的厚度不超过要求,每层抹灰的间隔时间不宜过短,要得等前层达到7~8成干时方可进行下层抹灰,严格按照配合比的要求搅拌砂浆,控制好砂浆的稠度。抹平后控制好最后收浆的时间,消除因砂浆收缩而产生的裂缝。
4.7层面防水:问题是起鼓和渗漏,采取的控制办法是所选用的防水材料必须有出厂合格证或检验报告,现场取样送检各项性能指标应符合规范要求。卷材施工前,屋面基层或保温层表面必须清理干净,干燥,泛水、落水窗口、伸缩缝等的防水构造处理必须认真细致,符合要求。基层处理剂必须刷透,卷材才能与基层牢固粘结,卷材的纵横搭接要符合规范要求,接缝处应封闭严密。
5结语
提高电力土建工程施工质量,在不断探索管理的新思路,探寻更为科学、先进的管理措施与技术,是每个电力工程企业共同追求的目标。不断完善企业管理及技术标准,努力提高施工质量,在激烈竞争的电力建设市场中,使企业能更好地生存、发展、壮大。