仪化一期工程以涤纶一厂为主体,包括热电厂、给排水厂、动力厂、供销公司、运输公司、生活区等配套工程,总建筑面积为72.32万平方米,总投资概算为10亿元,于1984年12月30日胜利实现投料一次成功。二期工程包括涤纶二厂、三厂、四厂(原研究所中间试验车间)和相应的水、电、汽、气等公用工程及辅助配套工程,分两个阶段进行建设。第一阶段,以涤纶二厂为主要建设项目,于1985年1月正式动工,1987年9月
The first phase of the project in Yihua is based on a polyester factory, including thermal power plants, water supply and drainage plants, power plants, supply and marketing companies, transportation companies, and residential areas. The total construction area is 723,200 square meters and the total investment is estimated at 1 billion yuan. , On December 30, 1984, the victory achieved a successful investment. The second phase of the project includes Polyester Plant No. 2, No. 3, and No. 4 (formerly the Institute’s intermediate test plant) and the corresponding public utilities such as water, electricity, gas, and gas, and ancillary ancillary works. The construction will be carried out in two phases. In the first stage, the second polyester plant was the main construction project. The construction was officially started in January 1985 and September 1987.