论文部分内容阅读
由哈尔滨汽轮机厂设计的1米长叶片设计方案技术审查会于1991年9月20~21日在北京召开。会议由能源部科技司和机电部—装司共同主持。会议听取了哈汽厂关于1米长叶片设计计算研究报告和东北电力设计院关于哈三工程600MW机组末级叶片由900mm改为1米后的技术经济分析。代表们认为
The technical review meeting of the 1-meter long blade design scheme designed by Harbin Turbine Works was held in Beijing from September 20 to September 21, 1991. The meeting was co-chaired by the Department of Science and Technology and the Department of Electrical and Mechanical Services of the Ministry of Energy. The meeting heard Harbin Steam Plant on the 1-meter-long blade design calculation report and Northeast Electric Power Design Institute on Ha-3 project 600MW turbine last stage blades from 900mm to 1 meter after the technical and economic analysis. The delegates think