许疃煤矿位于安徽省宿州市西南部,距宿州市37km,距蒙城县28km。其隶属于安徽省淮北矿业(集团)有限责任公司,矿井设计生产能力1.5Mt/a,采用立井分水平,集中石门、分组大巷开拓方式,初期工业场地内布置主井、副井。地面排矸系统初期采用二台250V电机车联合滚笼排矸石方式进行地面运输;后期考虑到架线电机车的架线会出现架线触电事故,
Xuzhou Coal Mine is located in the southwest of Suzhou City, Anhui Province, 37km away from Suzhou City and 28km away from Mengcheng County. It belongs to Anhui Huaibei Mining (Group) Co., Ltd. with mine design and production capacity of 1.5Mt / a. It adopts vertical shaft separation, centralized Shihmen and grouping and roadway development. The primary and auxiliary wells are arranged in the initial industrial site. Ground gangue system used by the early two sets of 250V electric locomotive roll cage gangue way for ground transportation; later consider the wired electric locomotive wiring there will be wire electric shock,