【摘 要】土钉墙支护是基坑支护工程中最常见的一种支护技术,本文提出了锚杆及土钉墙支护工程质量预控、土钉墙支护的常见质量问题及防治措施。
【关键词】锚杆;土钉墙;支护工程;质量问题;防治措施
The theory anchor man pole and soil nail a wall to protect engineering quality control
Huang Jie
(Shaoxin city real estate comprehensive development limited company Shaoxin Zhejiang 312000)
【Abstract】Soil's nailing a wall to protect is a Ji pit protect engineering in a kind of the most familiar protect a technique, this text put forward anchor man pole and soil to nail a wall to protect engineering quality to prepare to control, the soil nail a wall to protect of familiar quality problem and prevention and cure measure.
【Key words】Anchor man pole;The soil nail a wall;Protect engineering;Quality problem;Prevention and cure measure
随着国民经济的迅速发展,我国的基本建设规模越来越大,数量越来越多。深基础工程的应用越来越广泛,锚杆及土钉墙支护是深基础工程中最常见的一种支护技术,本文主要谈谈锚杆及土钉墙支护工程质量预控、质量问题及防治措施。
1. 锚杆及土钉墙支护工程质量预控
1.1 锚杆及土钉墙支护工程施工前应熟悉地质资料、设计图纸及周围环境,降水系统应确保正常工作,必需的施工设备如挖掘机、钻机、压浆泵、搅拌机等应能正常运转。
1.2 一般情况下,应遵循分段开挖、分段支护的原则;不宜按一次挖就再行支护的方式施工。
1.3 施工中应对锚杆或土钉位置,钻孔直径、深度及角度,锚杆或土钉插入长度,注浆配比、压力及注浆量,喷锚墙面厚度及强度、锚杆或土钉应力等进行检查。
1.4 每段支护体施工完后,应检查坡顶或坡面位移,坡顶沉降及周围环境变化,如有异常情况应采取措施,恢复正常后方可继续施工。
2. 锚杆及土钉墙支护工程常见质量问题及防治措施
2.1 锚具夹片滑脱,失去锚固作用。
2.1.1 质量问题:锚具在张拉锚固后不久,失去作用,即钢绞线在锚杆桩测试时不起拉结作用。
2.1.2 防治措施。
(1)夹片应采用表面渗碳工艺,提高硬度,使硬度达到50一55HRc。
(2)锚杆施工完后应重新检查锚头有无松动、脱落,必要时重新将锚头张拉一下。
(3)工厂交付锚具、夹片时应作详细检查验收、施工单位对锚具质量应切实负起责任。
2.2 锚杆不起作用,桩折断,吏扦结构倒塌。
2.2.1 质量问题:基坑挖到设计标高后,出现锚杆端部脱落,挡土桩连系横梁掉下,桩间土开裂,桩顶地面较远处发生裂缝,随后,桩被折断,支护结构倒坍,邻近自来水管断裂,边坡塌方,基坑泡水。
2.2.2 防治措施。
(1)预应力施工应由有经验技工操作,如无经验,应经过培训并由有经验工人予以指导,当锚头锚住后还应检查横梁 (一般为工字钢)是否受力。当发现横梁脱落,应立即停止挖土,分析原因,采取措施,如工地未能采取措施,则倒塌不可避免。
(2)基坑开挖掘进应作排桩的位移监测,以便及时发现桩有无大的位移,一且预报,应分析原因,采取措施。
2.3 锚杆与地下连续墙预留乳漏水涌砂。
2.3.1 质量问题:采用地下连续墙及锚杆支护的工程,一般在地下连续墙施工时,在墙上一定位置预留孔洞,以作钻孔和穿锚杆之间。钻孔和装设锚杆时,锚杆外套管与地下连续墙预留孔之间常存在空隙,造成水流通道,在地下压力水作用下,水和粉细砂大量涌人基坑内,或拨出钻杆时,导致大量泥沙流人基坑内,造成地面塌陷,邻近建筑物开裂。
2.3.2 防治措施。
(1)在孔口设橡胶垫圈,以阻止水和砂涌人基坑内。
(2)在钻杆钻进时,保持钻头与外套管有一定距离,停钻时缩回外套管内,防止水、砂从套鸳内进人基坑内。
(3)锚杆灌注锚固体砂浆时,应保持注浆压力不小于0.4~0.6MPa。
(4)拔管时应保留最后两节外套管,在水泥初凝后才拔出。
2.4 土钉墙支护设置不当导致邻近建筑物滑玻。
2.4.1 质量问题:土钉墙支护设置在填土、黏土和淤泥质土层上,坑底为3.0m以上淤泥质土层。土钉墙支护落在淤泥质土层上,单纯用土钉锚固,长度严重不足,承载力不够,加上坑底被动土区抗力低,施工时降排水不良,有地面、地下水渗人,土体稳定性差,从而导致支护失稳,使整个支护连动墙背土体绕基坑底滑坡,使邻近建筑物随之坍塌,最终倒塌。
2.4.2 防治措施。
(1)应根据地质和环境条件,应采取土层预应力锚杆与土钉墙结合的支护方案。在第一根土钉处改用预应力土层锚杆,其长度应通过邻近建筑物宽度,使达到较好土层;其每根土钉长度应按规范规定计算,一般宜上部设置的土钉较长而下部较短,并考虑邻近建筑物荷载的作用。
(2)施工过程中要做好排降水工作,防止地表水、地下水浸入边坡土体。
(3)施工前要作预应力土层锚杆、土钉与土体的极限摩阻力试验,作为设计的依据。施工过程中应作好监控,监测边坡和邻近建筑物的变形情况,发现倾斜、下沉、裂缝情况,及时进行处理。
参考文献
[1] GB 50007~2002建筑地基基础设计规范。北京:中国建筑工业出版社,2002
[2] JGJ79─91建筑地基处理技术规范,北京中国计划出版社,2002
[3] 高大钊,土力学与基础处理工程,北京:中国建筑工业出版社,1998
【关键词】锚杆;土钉墙;支护工程;质量问题;防治措施
The theory anchor man pole and soil nail a wall to protect engineering quality control
Huang Jie
(Shaoxin city real estate comprehensive development limited company Shaoxin Zhejiang 312000)
【Abstract】Soil's nailing a wall to protect is a Ji pit protect engineering in a kind of the most familiar protect a technique, this text put forward anchor man pole and soil to nail a wall to protect engineering quality to prepare to control, the soil nail a wall to protect of familiar quality problem and prevention and cure measure.
【Key words】Anchor man pole;The soil nail a wall;Protect engineering;Quality problem;Prevention and cure measure
随着国民经济的迅速发展,我国的基本建设规模越来越大,数量越来越多。深基础工程的应用越来越广泛,锚杆及土钉墙支护是深基础工程中最常见的一种支护技术,本文主要谈谈锚杆及土钉墙支护工程质量预控、质量问题及防治措施。
1. 锚杆及土钉墙支护工程质量预控
1.1 锚杆及土钉墙支护工程施工前应熟悉地质资料、设计图纸及周围环境,降水系统应确保正常工作,必需的施工设备如挖掘机、钻机、压浆泵、搅拌机等应能正常运转。
1.2 一般情况下,应遵循分段开挖、分段支护的原则;不宜按一次挖就再行支护的方式施工。
1.3 施工中应对锚杆或土钉位置,钻孔直径、深度及角度,锚杆或土钉插入长度,注浆配比、压力及注浆量,喷锚墙面厚度及强度、锚杆或土钉应力等进行检查。
1.4 每段支护体施工完后,应检查坡顶或坡面位移,坡顶沉降及周围环境变化,如有异常情况应采取措施,恢复正常后方可继续施工。
2. 锚杆及土钉墙支护工程常见质量问题及防治措施
2.1 锚具夹片滑脱,失去锚固作用。
2.1.1 质量问题:锚具在张拉锚固后不久,失去作用,即钢绞线在锚杆桩测试时不起拉结作用。
2.1.2 防治措施。
(1)夹片应采用表面渗碳工艺,提高硬度,使硬度达到50一55HRc。
(2)锚杆施工完后应重新检查锚头有无松动、脱落,必要时重新将锚头张拉一下。
(3)工厂交付锚具、夹片时应作详细检查验收、施工单位对锚具质量应切实负起责任。
2.2 锚杆不起作用,桩折断,吏扦结构倒塌。
2.2.1 质量问题:基坑挖到设计标高后,出现锚杆端部脱落,挡土桩连系横梁掉下,桩间土开裂,桩顶地面较远处发生裂缝,随后,桩被折断,支护结构倒坍,邻近自来水管断裂,边坡塌方,基坑泡水。
2.2.2 防治措施。
(1)预应力施工应由有经验技工操作,如无经验,应经过培训并由有经验工人予以指导,当锚头锚住后还应检查横梁 (一般为工字钢)是否受力。当发现横梁脱落,应立即停止挖土,分析原因,采取措施,如工地未能采取措施,则倒塌不可避免。
(2)基坑开挖掘进应作排桩的位移监测,以便及时发现桩有无大的位移,一且预报,应分析原因,采取措施。
2.3 锚杆与地下连续墙预留乳漏水涌砂。
2.3.1 质量问题:采用地下连续墙及锚杆支护的工程,一般在地下连续墙施工时,在墙上一定位置预留孔洞,以作钻孔和穿锚杆之间。钻孔和装设锚杆时,锚杆外套管与地下连续墙预留孔之间常存在空隙,造成水流通道,在地下压力水作用下,水和粉细砂大量涌人基坑内,或拨出钻杆时,导致大量泥沙流人基坑内,造成地面塌陷,邻近建筑物开裂。
2.3.2 防治措施。
(1)在孔口设橡胶垫圈,以阻止水和砂涌人基坑内。
(2)在钻杆钻进时,保持钻头与外套管有一定距离,停钻时缩回外套管内,防止水、砂从套鸳内进人基坑内。
(3)锚杆灌注锚固体砂浆时,应保持注浆压力不小于0.4~0.6MPa。
(4)拔管时应保留最后两节外套管,在水泥初凝后才拔出。
2.4 土钉墙支护设置不当导致邻近建筑物滑玻。
2.4.1 质量问题:土钉墙支护设置在填土、黏土和淤泥质土层上,坑底为3.0m以上淤泥质土层。土钉墙支护落在淤泥质土层上,单纯用土钉锚固,长度严重不足,承载力不够,加上坑底被动土区抗力低,施工时降排水不良,有地面、地下水渗人,土体稳定性差,从而导致支护失稳,使整个支护连动墙背土体绕基坑底滑坡,使邻近建筑物随之坍塌,最终倒塌。
2.4.2 防治措施。
(1)应根据地质和环境条件,应采取土层预应力锚杆与土钉墙结合的支护方案。在第一根土钉处改用预应力土层锚杆,其长度应通过邻近建筑物宽度,使达到较好土层;其每根土钉长度应按规范规定计算,一般宜上部设置的土钉较长而下部较短,并考虑邻近建筑物荷载的作用。
(2)施工过程中要做好排降水工作,防止地表水、地下水浸入边坡土体。
(3)施工前要作预应力土层锚杆、土钉与土体的极限摩阻力试验,作为设计的依据。施工过程中应作好监控,监测边坡和邻近建筑物的变形情况,发现倾斜、下沉、裂缝情况,及时进行处理。