针对2013工作面轨道顺槽受断层和软煤岩双重影响大量水和煤泥涌出、巷道不能按原设计方位通过断层的问题,通过对原巷道进行调线,提出了超前预注浆方案。分析了2013工作面轨道顺槽揭露断层的产状,根据巷道围岩实际情况,从注浆材料、参数选择、注浆孔布置等方面对巷道围岩超前注浆加固进行了设计,并对巷道支护方式进行了优化,使巷道顺利通过了断层。
In view of the fact that the orbital groove of 2013 facet is double affected by faults and soft coal rocks, a large amount of water and slime are gushing out. The roadway can not pass through the fault according to the original design orientation and the advanced pre-grouting scheme is proposed by adjusting the original roadway. According to the actual conditions of the surrounding rock of tunnel, the grouting material, parameter selection, the layout of grouting holes and so on are adopted to design the advanced grouting and reinforcement of the surrounding rock of the roadway, Supports have been optimized so that the tunnel passes the fault smoothly.