七里塘水电站导流洞衬砌后洞径为6m×7m,城门洞型,混凝土衬砌范围0+000m~0+150m,衬砌厚度50cm,双层钢筋。导流洞需在截流前完成衬砌及回填灌浆施工,工期极为紧张,如何在确保安全、质量的前提下尽快完成衬砌是制约大坝工程截流的关键项目。简易钢模台车采用脚手管搭设,行走装置采用橡胶钢轮,整个台车分两节组成,单节长度6m,组合长度12m。简易台车搭设、装模、拆模均快捷方便且成本低廉,确保了导流洞衬砌混凝土顺利完成。
The tunnel diameter of the diversion tunnel of Qitangtang Hydropower Station is 6m × 7m after lining. The diameter of the gate tunnel is between 0 + 000m and 0 + 150m and the lining thickness is 50cm. The diversion tunnel needs to be completed lining and backfill grouting construction before the river closure. The construction period is extremely tense. How to complete the lining as soon as possible to ensure the safety and quality is the key project to restrict the dam closure. Simple steel mold trolley erection using scaffolding, walking device using rubber steel wheels, the entire trolley is divided into two sections, the length of a single section 6m, the combined length of 12m. Simple trolley erection, mold loading, mold removal are quick and easy and low cost, to ensure the smooth completion of the diversion tunnel lining concrete.