简述了秦山300MW核电站放射性废物处理系统调试的主要项目、调试方法、调试过程发现的主要问题的处理、调试的结果和评价。放射性废气的处理采用压缩贮存和过滤的工艺流程。废气处理系统主要转动设备是膜式压气机。调试中,独创膜片充气法,在不损坏膜片的条件下,验证膜片破损报警和联锁停机的功能。放射性废液的处理采用蒸发和离子交换的工艺流程。系统试验项目比较多,主要有液位高值、低值报警;压力高值报警;液位、压力、
The main items of commissioning of radioactive waste treatment system of Qinshan 300MW nuclear power station, methods of debugging, handling of main problems found during commissioning, results of commissioning and evaluation are briefly described. Radioactive waste gas treatment using compressed storage and filtration process. Exhaust gas treatment system is the main rotating equipment film compressor. Commissioning, the original membrane aeration method, without damaging the diaphragm conditions, the diaphragm damage alarm and interlock shutdown function. Radioactive waste treatment using evaporation and ion exchange process. System test projects are more, the main high level, low alarm; high pressure alarm; level, pressure,