在水电资源开发逐渐开始向流域中上游、偏远地区、高寒高海拔地区转移的新形势下,传统调价方式已经显露出诸多问题。针对于此,提出采用合同价格实时动态化调整计算思路,以建设造价数据信息库为基础,采用实测工程所在地调价因子价格指数、每期实测调整期内调价因子权重的做法进行合同价格调整,与以往的传统做法相比,该方法能真实反映工程实际投资动态变化,具有对水电工程造价的动态管理的效果,通过实例测算情况来看可以进一步研究形成系统的动态调价手段。
Under the new situation that the development of hydropower resources gradually begins to shift to the upper and middle reaches of the basin, remote areas and alpine areas at high altitudes, the traditional price adjustment methods have revealed many problems. In view of this, this paper proposes to adopt real-time dynamic adjustment of contract price to adjust the calculation method, based on the construction of cost data information base, adjust the price of the contract by adjusting the price index of the project, Compared with the traditional methods, this method can truly reflect the dynamic changes of the actual investment in engineering and has the effect of dynamic management on the construction cost of hydropower projects. From the point of view of actual measurement, the method of dynamic price adjustment can be further studied.