2010年3月,某承包人承接某发包人的厂房工程,双方在施工合同中约定工程采用固定总价包干方式。同时约定设计变更、现场签证均须经总监理工程师现场签字确认并加盖监理单位专业章,经发包人现场负责人王某签字、加盖发包人公章后方有效。签证单必须在签证发生后的15日内办理完毕,承包人不按期上报签证资料,视同承包人认可该项费用已经包含在合同价款中,签字手续不全的资料,结算时按无效文件处理。2011年10月,工程通过竣工验
March 2010, a contractor to undertake a contractor plant project, the two sides agreed in the construction contract project using a fixed total package approach. At the same time, the design change and on-site visa are subject to the signature of chief supervising engineer and affixing the professional seal of the supervision unit. After signing the contract, Wang, the person in charge of the contractor, is valid after affixing the official seal of the contractor. The visa application must be completed within 15 days after the visa is issued. The contractor does not report the visa information on schedule, and is deemed the same as the contractor’s approval that the expense has been included in the contract price. In October 2011, the project passed the final inspection