论文部分内容阅读
进入春季以来,正是建筑施工的高峰时期,因建筑施工而影响电力设施正常运行的事时有发生。1996年9月11上午,江苏省邗江县瓜洲镇一建筑工程队在吊楼板时,因楼板吊起后旋转太快,碰到了10kV的瓜洲工业线上,造成了10kV“瓜工”线断线停电事故。9月12日上午,八里镇一单位在割除6m多高的废气管道时,由于承包人不注意周围的电力线路走向,在通气管道倒下时,砸在了10kV的八里工业线上,造成了10kV“八工”线断线停电事故。
Since entering the spring, it is the peak period of construction, and the normal operation of power facilities due to the construction of buildings has occurred from time to time. On the morning of September 11, 1996, a construction team at Guazhou Town, Qijiang County, Jiangsu Province, swung too fast when it was suspended due to the floor slab and hit the 10 kV Guazhou Industrial Line, resulting in a 10 kV “Guazao” line Disconnection power outage accident. On the morning of September 12, when a unit in Bali town excised a 6m-high exhaust pipe, the contractor did not pay attention to the surrounding power lines and plunged it into the 10kV Bali industrial line when the ventilation pipe fell down. As a result, 10kV “eight workers” line power outage accident.