北京图书馆新馆工程是国家重点项目,于1983年11月18日正式开工,工程总投资约二亿九千万元(其中建筑安装工程造价为13365万元),于1987年7月1日完成。比国家定额工期提前二年零四个月,比与建设单位订立的合同工期提前了一年零二个月。本工程由北京市第三建筑工程公司、北京市设备安装公司和北京市机械施工公司具体施工,全部栋号工程质量优良,安全无事故,工程成本降低5%,做到了高速、优质、安全、低消耗。
The new project of the Beijing Library is a national key project. It was formally started on November 18, 1983. The total project investment was about 290 million yuan (including the construction and installation project cost of 133.65 million yuan) on July 1, 1987. carry out. It is two years and four months ahead of the national fixed schedule, one year and two months earlier than the contract period with the construction unit. This project was specifically constructed by Beijing No.3 Construction Engineering Company, Beijing Equipment Installation Company and Beijing Machinery Construction Company. All the Donghao Projects are of high quality, safe and free from accidents, and the project cost is reduced by 5%, achieving high speed, high quality, safety, Low consumption.