针对生物制药厂房荷载大、柱网大、层高高的特点,对不同烈度区(7、8度)、不同场地类别(II、III类)的多层框架结构生物制药厂房进行多次计算,得出了生物制药厂房结构在不同楼面活荷载、不同梁板布置时的主要梁柱截面、混凝土用量、钢筋用量。同时也对新、旧抗震规范对此种厂房工程量的影响进行了对比。通过分析,对多层框架结构生物制药厂房进行优化设计,可供确定方案时估算工程量,给以后类似工程提供参考。
According to the characteristics of biopharmaceutical factory such as large load, large column net and high storey height, the multi-layer framework biopharmaceutical factory building in different intensity areas (7 and 8 degrees) and different site categories (II and III) The main beam and column sections, the amount of concrete and the amount of steel used in living floor of different biochemical pharmacy structures at different floors were obtained. At the same time, the impact of new and old seismic codes on the amount of such works is also compared. Through the analysis, optimize the design of biopharmaceutical factory building with multi-layer frame structure, which can be used to estimate the project volume when determining the scheme and provide reference for similar projects in the future.