首先介绍了OPEN2000能量管理系统(EMS)中适应控制性能评价标准(CPS)的新的自动发电控制(AGC)控制策略;然后,结合AGC软件包在云南电网实际运行中的经验,提出了正确设置AGC控制策略中相关参数的方法。这些方法有利于提高南方电网频率控制质量,体现在紧急情况下云南电网对南方电网的频率支援,为南方电网即将实施的CPS标准考核进行了充分的技术准备。
First of all, a new automatic generation control (AGC) control strategy for adaptive control performance evaluation (CPS) in OPEN2000 energy management system (EMS) is introduced. Then, based on the experience of AGC software package in actual operation of Yunnan Power Grid, the correct setting AGC method of control strategy related parameters. These methods are conducive to improving the frequency control quality of China Southern Power Grid, embodying the frequency support of China Southern Power Grid by Yunnan Power Grid in case of emergency, and fully preparing for the forthcoming CPS standard assessment of China Southern Power Grid.