混凝土面板堆石坝,是当前广泛采用的坝型。其设计导则、施工规范等国家均以发布并实施,但在工程造价方面,缺乏统一概预算定额子目,使在工程建设经济评价及招投标计价方面没有统一的标准。根据混凝土而板坝施工的记录、测算、对比分析,并根据《水利水电建筑工程预算定额》1987、《水利水电建筑工程补充预算定额》1994的编制水平,中国水利水电第十二工程局编制了趾板混凝土浇筑、坝体垫层料填筑、坝体过渡料填筑、面板止水共4项定额,可供参考。
Concrete face rockfill dam, is currently widely used dam type. Its design guidelines, construction codes and other countries are released and implemented, but in the project cost, the lack of unified budget subheads, so that there is no uniform standard in the economic evaluation of construction and bidding. According to the records of concrete slab construction, calculation and comparison analysis, and according to “water conservancy and hydropower construction budget quota” 1987, “water conservancy and hydropower construction project supplementary budget quota” 1994 compilation level, China Water Conservancy and Hydropower Engineering Bureau twelfth prepared Toe plate concrete pouring, dam body cushion material filling, dam fill material filling, panel water stop a total of 4 fixed, for reference.