论文部分内容阅读
一、滨南油田滨三区掺水流程滨三区是七六年下半年的新开发区。全区规划油水井56口,计量站5座,联合站1座。因油品粘度较高,原设计就是双管掺水流程。目前全区已完钻井46口,建成投产油井28口,2、3、4号计量站已建成投产。1、5号站还未建成,全区日产油量200T/日。原油物性:比重:0.9 粘度(50℃):25~1900厘泊凝固点:20~32℃
First, Binnan Oilfield Bin three districts water blending process Bin three districts in the second half of 1976 the new development zone. The region planning 56 wells, 5 metering stations, a joint station. Due to the higher viscosity of the oil, the original design is double pipe water flow. At present, the region has completed drilling 46, completed and put into operation 28 wells, 2,3,4 measurement stations have been completed and put into production. 1,5 stations have not yet completed, the region Nissan 200T / day. Crude Properties: Specific gravity: 0.9 Viscosity (50 ℃): 25 ~ 1900 centipoise Freezing point: 20 ~ 32 ℃