一、生产概况十高炉于1963年12月27日大修竣工后投入生产,由于它成功地利用自熔性烧结矿开炉,从而促使开炉后各主要技术经济指标迅速地达到正常生产的水平(见表1)。十高炉生产的强化,分为两个阶段,开炉后1至3月份为第一阶段,该期强化速度较慢,利用系数由1.320至1.563,操作中除采用高风温和高压(0.5—0.8公斤/厘米~2)外,更突出的是在炉料顺行的情况下,积极改进操作,大
First, the production profile Ten blast furnace December 27, 1963 overhaul completed and put into production, due to its successful use of self-fluxing sinter open the furnace, which led to open the furnace after the main technical and economic indicators quickly reach the level of normal production ( See table 1). Ten blast furnace production intensification, divided into two phases, after the furnace from January to March for the first phase, the strengthening of slower, the utilization factor from 1.320 to 1.563, except for the operation of high wind temperature and high pressure (0.5-0.8 Kg / cm ~ 2), the more prominent is the charge in the case of the forward, and actively improve the operation of large