首钢二烧结主厂房高跨是一个高层钢筋混凝土框架结构,其轴线面积为531平方米,有18个不同断面的变柱,主次梁共14个层次,计232根,牛腿108个,分布于74个不同的标高上,滑升高度为44.7米,混凝土用量1000立方米。面对这样一个复杂的结构,我公司广大职工在党委领导下,以批林批孔为纲,破除迷信,解放思想,发扬敢于革命、敢于创
The high-span Shougang No. 2 Sintering Workshop is a high-rise reinforced concrete frame structure with an axis area of 531 square meters and 18 different sections of variable columns. The main and secondary beams total 14 levels, 232 and 108. Distribution At 74 different elevations, the sliding height is 44.7 meters and the concrete volume is 1000 cubic meters. In the face of such a complex structure, the majority of employees of our company under the leadership of the party committee, with the approval of Lin Piao Kong as the guideline, break the superstition, emancipate the mind, carry forward the courage to revolutionize, dare to create