地下室施工分标段执行过程中,较容易出现之前施工不足影响后续施工的过程。本文项目施工中出现了桩基支护入侵建筑主体空间的情况。本文通过成本最低的施工方法,对此瑕疵进行了处理,得到了投资方和监理方等其他合作单位的一致好评。本文采用的处理方式为预打锚索、割除入侵部分、墙板单面植筋加固、重挂网、混凝土补充浇筑等系列处理方法。
Sub base construction sub-standard section of the implementation process, the more likely to occur before the construction of the subsequent construction process. This article project construction appeared in the invasion of pile foundation support the main construction space. This article through the lowest cost construction methods, dealing with this flaw, by investors and supervisors and other cooperation units of praise. In this paper, the treatment method is pre-playing anchor cable, cut off the intrusion part of the wall panel planting reinforcement, re-hanging net, pouring concrete and other series of treatment methods.