1月16日,轨道交通莘闵线工程筹建处提出工程网络节点计划基本框架。主要是:1999年上半年基本完成沿线工程用地拆迁及“三通一平”,7月1日工程正式开工;2001年底全线贯通,车辆、设备安装全部到位;2002年7月1日起对外试运营。 1月21日,苏州河综合整治一期工程确定今年计划进度节点目标。主要是:支流污水截流南片工程年内部分泵站下部结构施工,干管完成30%;北片工程年内泵站下部结构开始施工,干管完成20%。7条支流建闸控制3月完成前期动拆迁,6月开始主体结构施工,年内建成泵站。综合调水吴淞路桥闸改造3月开工,主汛期前完成设备改造,年底完成防渗工程;上游疏拓工程年内完成5%;东大盈泵站4季度开工。虹口港、杨浦港旱流污水截流工程泵站连接管道7月份开始施工,年底工程全面开工,中途、溧阳、霍山泵站完成下部结构。石洞口城市污水处理厂9月完
On January 16, the Rail Transit Line Construction Office proposed the basic framework of the project network node plan. Mainly: in the first half of 1999, land acquisition along the project line was basically completed, and “three links and one leveling” were completed. The project was formally started on July 1. The entire line was completed at the end of 2001, and all the vehicles and equipment were installed; the trial operation began on July 1, 2002. . On January 21st, the first phase of the Suzhou Creek Comprehensive Improvement Project determined the planned schedule goals for this year. Mainly: the construction of the substructure of some pumping stations during the south section of the tributary sewage interception project, 30% of the dry pipe was completed; the construction of the lower part of the pump station started during the year of the northern project, and 20% of the dry pipe was completed. The construction of the 7 tributaries was completed in March, and the main structure was constructed in June. The pump station was built during the year. The comprehensive water transfer Wusong Road Bridge Gate reconstruction will be started in March, the equipment renovation will be completed before the main flood season, and the anti-seepage project will be completed by the end of the year; the upstream sparse expansion project will complete 5% within the year; Dongda Ying Pumping Station will start construction in the fourth quarter. The construction of the connecting pipelines of the pumping station for the sewage interception works of Hongkou Port and Yangpu Port was started in July. The project was fully started at the end of the year, and the lower structure was completed at the Midway, Fuyang and Huoshan Pumping Stations. Shidongkou Urban Sewage Treatment Plant finished in September