江苏省灌云县长达20公里的新沂河大堤除险加固工程,经过两万余名民工连续两个月的艰苦奋战,于1月5日全面完成,提前竣工。这项工程核定正项土方104万立米,正杂项总工日104.6万个,总投资216.8万元。原计划1983年11月上旬开工,今年1月中旬完成。灌云县地处沂、沭、泗诸河下游,是洪水走廊,防洪保安不仅关系到农业翻番的大事,也是保障全县人民生命财产安全的当务之急。县委,县政府对新沂河大堤除险加固工程十分
Guanyun County, Jiangsu Province, up to 20 kilometers Xinyi embankment reinforcement project, after more than 20,000 migrant workers for two months of hard work, completed on January 5, completed ahead of schedule. The project approved an official earth 1.04 million cubic meters, is 104.6 million total working days, with a total investment of 2.168 million yuan. The original plan started in early November 1983, completed in mid-January of this year. Guanyun County is located in Yi, Shu, Si River downstream, flood corridors, flood control and security is not only related to agriculture, double the important event, but also to protect the lives and property of the county’s top priority. County Party committee and county government Xinyi embankment reinforcement project is very