论文部分内容阅读
石泉水电站位于汉江上游距石泉县城一公里的峡谷出口处,坝高65米,坝长353米;库容4.7亿米~3,正常高水位410米,死水位393米。电站装机容量13.5万千瓦(3.台单机容量4.5万千瓦机组),最大发电能力可达15余万千瓦,枯水期最小月平均出力3~3.5万千瓦,保证出力3.2万千瓦,多年平均发电量6.3亿度。电站
Shiquan Hydropower Station is located in the upper reaches of the Hanjiang River from Shiquan County one kilometer at the exit of the canyon, dam height of 65 meters, 353 meters long dam; storage capacity of 470 million meters to 3, the normal high water level of 410 meters, 393 meters of stagnant water. Power station installed capacity of 135,000 kilowatts (3. Taiwan single unit capacity of 45,000 kilowatts units), the maximum generating capacity of up to 15 million kilowatts, dry month average monthly output of 3 to 35,000 kilowatts, to ensure that the output of 32,000 kilowatts, years of average power generation 6.3 Billion degrees. Power station