几年来,我行积极协助锦州电厂加强投资管理,合理使用建设资金,为国家节约建设资金和制止不合理开支达3,858.3万元,占概算投资的10%. 一、深入调查,协助选择合理的建设方案电厂贮灰大坝设计采用堆石坝,需采石68万立方米,堆石50万立方米,投资834万元.我们想,贮灰坝不同于水库坝,粉煤灰沉淀后稳定紧固,冲击力不大,不需全部采用石头砌筑,可以用砂石混合砌筑,坝体里外砌石护坡.为了做到切实可行,我们先到锦县水利局请教,又和电厂专业人员从技术、经济、结构上反复探讨,取得了一致意见,还到现场对料源进行实地调查,确认现场附近鹅卵石可以满足工程需
Over the past few years, ICBC has actively assisted Jinzhou Power Plant to strengthen investment management and rationally use construction funds to save construction funds and stop unreasonable expenditures for the country by 38.587 million yuan, accounting for 10% of the estimated investment. In-depth investigation to assist in the selection of reasonable construction The power plant ash storage dam is designed to use a rockfill dam, which requires 680,000 cubic meters of quarrying, 500,000 cubic meters of rockfill, and an investment of 8.34 million yuan. We think that the ash storage dam is different from the reservoir dam, and the fly ash is stable after settling. Solid, not much impact, do not need to use all stone masonry, can use sand and stone mixing masonry, dam body inside and outside stone masonry slope. In order to be practical, we first consult the Jinxian Water Conservancy Bureau, and professional power plants From the technical, economic, and structural perspectives, the staff repeatedly discussed and obtained consensus. They also went to the site to conduct field surveys on the source and confirmed that the pebbles near the site can meet the needs of the project.