论文部分内容阅读
上海宝山钢铁总厂是我国目前最大的建设项目,建成后将年产钢水671万吨、钢材422万吨、铁650万吨。一期工程(除140无缝管厂外)已于1985年9月投入生产。二期工程正在建设中,它主要包括4000m~3高炉一座、450m~3烧结机一台、50孔焦炉四座、1900mm 板坯连铸机二台、2050mm 带钢热连轧机一套、2030mm 冷轧扳机一套以及相应公用辅助设施。1986年8月,机械部通用零件局在宝钢召开了液压、气动元件等产品现场服务会。对宝钢一期工程的备件国产化问题,与宝钢有关部门进行了商讨。一期工程中,140无缝管厂是太原重机厂与联邦德国德马克公司合作制造的,液压、气动件全部从联邦德国力士乐公司引进;其余设备主要由日本新日铁(株)制造,液压、气动元件涉及
Shanghai Baoshan Iron and Steel Plant is currently China’s largest construction project, after the completion of an annual output of 6.71 million tons of molten steel, 4.22 million tons of steel, 6.5 million tons of iron. The first phase (except 140 seamless pipe factory) was put into production in September 1985. The second phase of the project is under construction. It mainly includes one 4000m ~ 3 blast furnace, one 450m ~ 3 sintering machine, four 50-hole coke ovens, two 1900mm slab caster and one set of 2050mm strip hot rolling mill with 2030mm cold A set of trigger and corresponding public auxiliary facilities. In August 1986, General Parts Department of Machinery Department held a field service meeting of hydraulic and pneumatic components in Baosteel. Baosteel on the issue of the localization of spare parts for the first phase, held discussions with the relevant departments of Baosteel. In the first phase, 140 seamless pipe factory was manufactured by Taiyuan Heavy Machinery Factory in cooperation with the Federal Republic of Germany Demark, all the hydraulic and pneumatic parts were imported from the Federal Republic of Germany Rexroth; the rest of the equipment was mainly manufactured by Japan’s Nippon Steel Corporation, Hydraulic, pneumatic components involved