2002年4月14-17日,委质监分站察尔森水库除险加固遗留工程质量监督项目站,对正在施工的察尔森水库除险加固遗留工程进行了检查。察尔森水库除险加固遗留工程2001-2002年施工建设项目包括9个部分:①溢洪道左侧加固;②输水洞进口加固;③大坝低部位护坡加固;④泄洪洞出口消能;⑤泄洪洞尾水渠加固;⑥厂房后山坡加固;⑦
From April 14 to April 14, 2002, the Quality Supervision and Surveillance Station of Qiersen Reservoir Reinforced and Remolded Project Quality Supervision Station left over was examined for the remaining works of reinforcement and reinforcement of the Chaersen Reservoir under construction. The remaining construction of the Chaersen reservoir reinforcement project 2001-2002 construction project consists of nine sections: ① spillway reinforcement on the left; ② water tunnel reinforcement; ③ slope dam reinforcement in the lower part of the site; ④ flood discharge outlet energy dissipation; ⑤ Drainage tunnel tail canal reinforcement; ⑥ plant slope reinforcement; ⑦