论文部分内容阅读
巴西的特雷斯伊尔莫斯电站是蒂埃特河上的最后一级电站,装机八台,容量1292MW。该电站的设计几乎成了巴西乃至整个南美洲的特征。开凿一条运河联结水库,从而充分利用高水头发电。电站设有两座船闸,使蒂埃特河、巴拉那河和巴拉那伊巴河之间能顺利通航。这个水电站包括一座土坝、一座混凝土坝、厂房,变电所和配电厂房等。大坝和厂房全长3710m(右岸1610m、左岸1620m,混凝土建筑480m)。
The Tres Ilmers Power Station in Brazil is the last station on the Teide River with an installed capacity of 1292 MW. The design of the plant has become almost a feature of Brazil and even throughout South America. Cut a canal linking reservoirs to make full use of high-head power generation. The power station has two locks to allow for smooth navigation between the Tete, the Paraná and the Paraná Iba. This hydropower station consists of an earth dam, a concrete dam, a factory building, a substation and a power distribution house. The dam and plant are 3710m in length (1610m on the right bank, 1620m on the left bank and 480m in concrete buildings).