3月28日,施工单位中铁十局集团有限公司进驻新野。4月26日,上庄拌合站及新甸拌合站全部完工并通过验收;4月28日,新野南梁场完工并通过验收;5月9日,新野北潦河特大桥第一桩开钻;5月13日,新野南梁场首片梁开始浇筑……不到两个月的时间里,新野一次次创造了高铁历史上的最快速度。作为河南“米字形高铁”线路的重要组成部分,郑万高铁具有重要战略意义。郑万高铁新野段项目自开工建设以来,新野县委、县政府站位全局,用“新
March 28, the construction unit in the Bureau of China Railway Group Co., Ltd. stationed in Shinano. On April 26, Shangzhuang Mixing Station and Xindian Mixing Station were all completed and passed the inspection. On April 28, Xinye Nanliangchang was completed and passed the inspection. On May 9, the first pile of Xinye Beiliaohe Bridge was opened Drilling; May 13, Shinano Nan Liangchang first piece of beam began to pouring ... ... less than two months time, Shinano again and again created the fastest high-speed rail in history. As an important part of Henan ”rice-shaped high-speed rail “ line, Zheng Wan high-speed rail has important strategic significance. Zhengwan high-speed rail project since the start of construction of a new field, the Xinye county government stationed the overall situation, with ”new"