中沧输气管道因服役年限较长,部分管道发生严重腐蚀。通过天然气管道改线置换对部分管段进行换管和增加埋深改造,为不影响下游用户用气,工程采用一级动火作业。描述了动火作业的方案设计和操作步骤。从阀门和仪表的调试、氮气置换、故障预测与处理、天然气置换、严密性试验等方面介绍了置换投产过程。严重腐蚀管段经过改造,阀门内外漏现象得到改善,管道阴极保护率明显提高,可为同类工程施工提供参考。
Cangcang gas pipeline due to longer service life, some serious corrosion of the pipeline. Through the replacement of natural gas pipelines to some of the pipe sections for pipe replacement and increase the depth of the transformation, in order not to affect the downstream gas users, the project uses a first-class hot work. Describes the program design and operation steps of hot work. From the valve and instrumentation debugging, nitrogen replacement, fault prediction and treatment, natural gas replacement, rigorous testing and other aspects of the replacement process introduced. Severe corrosion After the transformation of the pipe, the valve inside and outside the phenomenon of leakage has been improved, significantly improve the cathodic protection of the pipeline, for the construction of similar projects provide a reference.