我处砂石料加工系统,因受地形限制,采料场与筛分系统两地高差较大。为解决这一差距,在粗碎机与半成品堆场之间,设一明溜槽。但在结构设计时,由于对输送的物料性质认识不足,造成投产后不久,混凝土构筑物磨损与槽内堆积拥高非常严重,影响了生产和安全。(一)明溜槽结构明溜槽长度68.2米,落差45.5米,倾斜度41°50′52″,底宽1.2米,侧墙高2.0米,为梯形断面。为抗磨起见在底板内铺有38公斤/米型钢轨七根用200号混凝土衬砌。侧墙用混凝土浇筑。投产后磨损严重部位及采取加固扩修方法,参看下图。
I sand aggregate processing system, due to topographical constraints, mining yard and screening system, a large difference between the two places. To solve this gap, between the crusher and semi-finished products yard, set a clear chute. However, in the structural design, due to the lack of understanding of the nature of the material being transported, shortening of putting into operation shortly after the concrete structure is worn out and accumulation in the tank is very serious, affecting production and safety. (A) Ming chute structure The chute length of 68.2 meters, 45.5 meters gap, slope 41 ° 50’52 ", the bottom width of 1.2 meters, 2.0 meters high sidewall, trapezoidal cross-section. Kilograms / meters of steel rails with seven 200 with concrete lining. Side wall with concrete pouring. Put into operation after the serious parts of the wear and reinforcement and expansion methods, see below.