前言我处辖堤荆江河段,根据多年实践经验,过去做护岸工程,对水下施工护脚部份,总是先抛枕(或沉笼、沉排)再抛石,以增强工程的整体性与适应性,起到复盖岸坡、抑制水流掏刷,收到了护岸的效果。但抛枕造价较高、用料量大、占甩劳力多、施工期长。为了探索护岸工程新办法,总结以往护岸工程的经验,在确保工程效果的前提下,力求降低工程费用,
Foreword I have jurisdiction over the embankment Jingjiang River, according to many years of practical experience, in the past to do bank protection works, the foot of the sub-construction of the foot, always throw the pillow (or cage, sink row) and then riprap to enhance the overall project Sex and adaptability, to cover the bank slope, inhibit the flow of digging brush, received the effect of revetment. However, the higher cost of throwing the pillow, using a large amount of materials, accounting for more labor, long construction period. In order to explore a new approach to bank protection projects, summarize the experience of bank protection projects in the past, and strive to reduce construction costs under the premise of ensuring the project results,