达成铁路遂宁涪江特大桥自1992年10月开工建造,至1994年9月,141个墩台已建成,5孔64米下承式栓焊钢梁已拼架完毕,只待架设其它厂制预应力混凝土梁和铺轨了。如今,一座飞跨涪江东西的长龙已屹立在遂宁市城北。这是继宝成铁路绵阳涪江大桥之后,涪江上建造的第二座铁路桥。 本桥位于达成线中段,在遂宁市城北约5公里处跨涪江。桥址处主河槽宽约1.2公里,枯水期水面宽约100米。全桥由133孔32米的预应力混凝土梁,2孔24米的预应力混凝土梁及5孔64米下承式栓焊钢桁梁组成。桥全长4738.55米,共有墩台
Achieved Railway Suining, Fujiang Grand Bridge started construction in October 1992 to September 1994, 141 piers have been completed, 5 holes 64 meters under the through bolt welded steel girders have been spell-framed, only to be erected other plants Prestressed concrete beams and laid out. Today, a long dragon flying across the Fujiang River has stood in the north of Suining City. This is the second railroad bridge built on the Fujiang River following the Fujiang River Bridge at Bao-Cheng Railway. The bridge is located in the middle reaches of the line, about 5 km north of Suining City across Fujiang. The main channel at the bridge width of 1.2 km wide, dry water surface width of 100 meters. The bridge consists of 133 holes 32 meters of prestressed concrete beams, 2 holes 24 meters of prestressed concrete beams and 5 holes 64 meters under the thimble welded steel truss beams. Bridge a total length of 4738.55 meters, a total pier