我厂今年的基本建設工程量很大,部批准的項目計有:延长联合儲庫30米,增建碎石庫两座、碎石烘干机一台、循环水池一座、深井六眼、各种管道三公里,购置2.5立方米电鏟一台、翻斗汽車四辆、水泥磨电收尘器两台等。这些項目都是列入企业調整規划,提高企业綜合生产能力的重要工程,大部分都要求在雨季之前全部竣工投入生产。我們面对这样繁重的基建任务,在一手抓生产的同时,一手抓基本建設,自始至終沒有放松。經过几个月的
The amount of capital construction work for this year’s plant is very large. The projects approved by the Ministry include the extension of 30 meters of joint storage, the addition of two gravel stores, a gravel dryer, a circulating pool, six deep wells, and each Three kilometers of pipelines were purchased, one 2.5 cubic meter electric shovel, four dump trucks, and two cement dust collectors were purchased. These projects are all important projects listed in the enterprise adjustment plan to improve the overall production capacity of enterprises. Most of them require completion of production before the rainy season. In the face of such a heavy infrastructure task, we have grasped the basic construction on the one hand, and have not relaxed from beginning to end. After several months