中核集团三门核电有限公司成立于2005年4月,承担着全球首台AP1000三代核电机组的建设重任,共规划建设6台125万千瓦的核电机组,总装机容量750万千瓦,分三期建设,预计2020年前全部建成,总投资超过1000亿人民币。一期工程于2009年4月19日正式开工,投资约400亿,是浙江省有史以来投资最大的单项工程,还是我国首个三代核电自主化依托项目,也是中美两国最大的能源合作项目。
Nuclear Group Sanmen Nuclear Power Co., Ltd. was established in April 2005 and undertakes the construction task of the first AP1000 nuclear power generation unit in the world. It plans to build 6 sets of 1.25 million kilowatts of nuclear power generating units with a total installed capacity of 7.5 million kilowatts and construction in three phases It is estimated that all of them will be completed before 2020 with a total investment of more than 100 billion yuan. The first phase of the project was officially started on April 19, 2009 with an investment of about 40 billion yuan. It is the largest individual project ever invested in Zhejiang Province or the first independent reliance project of China’s three generations of nuclear power generation and the largest energy cooperation project between China and the United States .