1982年10月,大庆油田采油六厂一矿新中转站的抽油机井开始投产。新中转站采用双管掺热水保温流程。中转站把大站来的水进加热炉里加热,经掺水泵打至计量间,再分配到各井,和井液掺合后返回。各井的掺水量是用阀门控制(计量间没装流量计)。投产后,发现以下几个问题:①一些产量低、距离近的井,回油温度和掺水温度相同;而一些产量高距离远的井,却经常因掺水过不去而堵塞管线;②各个计量间掺水压力不平衡,压力高的达0.5MPa,低的只有0.35MPa。掺水压力低的油井压力稍高一点就掺不进水,需
In October 1982, the pumping station of the new transfer station of the No. 6 Mine of Daqing Oilfield started its operation. The new transfer station using double heat pipe insulation process. Transfer station to the station to the heating water into the heating furnace, the water pump hit the metering chamber, and then assigned to the wells, and well mixed with the return. The amount of water in each well is controlled by a valve (there is no meter installed between the meters). After put into production, the following problems were found: ① Some wells with low output and close distance have the same oil return temperature and water mixing temperature; while some wells with high output and high distance often block the pipeline due to excessive water intake; ② Each measurement Water pressure imbalance between the pressure up to 0.5MPa, low only 0.35MPa. Low oil pressure wells slightly higher pressure on the mixed with water, required