论文部分内容阅读
我矿提升系统为塔式多绳摩擦提升,井下有-215m、-295m二处装矿站,均采用气动缸进行装料,井上为曲轨卸矿。现提升系统每天平均提升1800t矿石、毛石,提升量为5.5t/箕斗,每次提升-215m和-295m平均运行用时(往返)3min,每次装矿及卸矿各用时14s。-215 m装矿站、-295m装矿站各有一大一小2个气缸,二处各配备1个气水分离器,井塔三楼有分配气缸2个,配备1个气水分离器。
Mine mine lifting system for the tower multi-rope friction upgrade, there are underground -215m, -295m loading station, are used pneumatic cylinder loading, upstairs curved track unloading. At present, the average daily lifting capacity of the system is 1800 tons of ore and rock, with an increase of 5.5 tons / bucket. The average operating time (round trip) of -215 m and -295 m is 3 minutes, and each loading and unloading time is 14 seconds. -215 m loading station, -295m loading station, one large and one small 2 cylinders, two gas-water separators at each of the two sites, two distribution cylinders at the third floor of the well tower, and one gas-water separator.