公安部(厦门)“9.18”工程度假酒店位于厦门黄盾环岛路以南的临海地段。地上四层,地下一层,总建筑面积7562.95m’。该建筑物总长68.4m,总宽36.35m。本工程设置一条南北方向长3635m,宽0SOm的后浇带。以下简述该工程后浇带施工的技术措施。l、后烧带的设置原设计后浇带
The Ministry of Public Security (Xiamen) “9.18” Project Holiday Hotel is located in the Linhai section of Huangdun roundabout road in Xiamen. It has four floors above ground and one basement level with a total construction area of 7562.95m’. The building has a total length of 68.4m and a total width of 36.35m. A post-pouring zone with a length of 3635 m in the north-south direction and a width of 0 SOm is set in this project. The following briefly describes the technical measures for the construction of post-concrete strips. l. After setting the original design of the belt after the pouring belt