论文部分内容阅读
摘要:
中小河流堤防的的安全关系到城乡居民生命财产的安危,本文以牡丹江干流防洪工程(二期)水毁修复工程为例,将已建防洪工程遭受“7.28”洪水损毁的堤段恢复重建设计,同时针对其施工难点,采取有针对性的施工措施,确保了施工质量,取得了良好的效果,为类似地质工程的堤防修复设计与施工提供了经验。
关键词:堤防水毁修复,加固设计,稳定性预算,施工要点
Abstract:Small river embankment safety relates to the urban and rural residents of life and property safety, this paper takes mudanjiang river flood control project (phase ii) waterlogging repair project as an example, the flood control works will have been built by the \"7.28\" flood damaged some reconstruction design, for its construction difficulties at the same time, targeted the construction measures, to ensure the construction quality, achieved good effect, for the similar geological engineering of dyke repair design and construction experience.
Keywords: repair damaged by flood embankment reinforcement design, budget stability, construction key points
中圖分类号: TM421;TM63 文献标识码:A
1工程概况
1.1项目概况
牡丹江干流防洪工程(二期)沿江受保护的乡镇有6个,分别是贤儒镇、红石乡、江南镇、黑石乡、靑沟子乡、大山镇,保护人口2.3万人,耕地13万亩。原设计堤防总长50.28km,回水堤长8.05km,支流规划堤防长度3.3km(西黄泥河左岸2.7km,大石河左岸0.6km),排水涵闸23座,防洪闸1座,疏通黑石电站下游河道工程。乡镇段堤防工程在遭受“7.28”大洪水后各乡镇均出现了不同程度的损毁,靑沟子林江堤防冲刷严重。
1.2原项目设计情况
1)防洪标准。敦化市牡丹江干流(靑沟子林江)堤防为牡丹江干流防洪工程的二期工程(即乡镇段),堤防防洪标准为30年一遇洪水,堤防级别为3级。排涝洪水标准为10年一遇洪水。
2)原设计洪水。靑沟子林江堤防设计洪水根据下游大山嘴子水文站按面积比的0.68次方关系确定,设计洪峰流量为2670m3/s。
3)工程任务和规模。敦化市牡丹江干流防洪工程(二期)靑沟子林江堤防原设计的主要任务是将防洪标准提高到30年一遇标准,保护总人口320人,耕地250hm2。敦化市牡丹江干流防洪工程(二期)靑沟子林江堤防原设计干流总长3.2km,回水堤1.75km,排水涵闸1座。
4)实施情况。根据设计批复文件及设计报告二期工程于2000年进行了开工建设。靑沟子林江堤防按设计完成干流3200m的土堤填筑,护坡及护脚均未完成。
2水毁修复设计方案
2.1设计原则
本次设计的原则是将已建防洪工程遭受“7.28”洪水损毁的堤段恢复重建,达到原设计标准;未按原设计修建完成在“7.28”洪水作用下造成严重损失的地段,应按原设计进行重建后达到原设计标准。因此本次牡丹江干流防洪工程(二期)靑沟子林江堤防水毁修复工程设计的堤防防洪标准及排涝洪水标准仍采用原设计标准。
2.2工程设计
2.2.1堤顶宽度及堤坡
原设计堤防横断面形式为斜坡式土堤,堤顶宽度为3.0m。堤防的临水侧边坡1:2.0,背水侧边坡1:2.5。
2.2.2干流桩号0+800m处管涌处理设计
由于管涌形成原因不详,为安全起见,因此本次设计将管涌处两侧各10m范围内(即桩号0+790m~0+810m)全部挖除后进行重新填筑,堤顶高程为原设计高程。
2.2.3干流堤脚加固设计
由于干流段3200m(桩号0+000m~3+200m)堤脚及堤坡实施时并未按原设计及批复标准完成,遭受“7.28”洪水淘刷后堤脚坍塌严重,近乎垂直坡度,为了确保堤防安全,本次设计将干流段堤脚进行加固处理。加固措施采取石笼沉排护脚,护脚顶高程根据石笼厚30cm。为了使石笼沉排护脚更加稳固,并且此段为水下作业,因此先抛投砂袋土堆成1:2.5的坡后在其上放石笼。护脚顶高程为实际地面高程,为确保堤脚稳固,在护脚顶部设2.0m的石笼平台;护脚底高程为河底线,石笼沿河底水平延伸3.0m。
2.2.4回水堤恢复重建设计
在“7.28”洪水作用下民筑回水堤发生决口100m(桩号3+200m~3+300m),本次设计将决口段堤基的覆盖层清除0.5m左右后重新填筑,堤顶高程达到原设计顶高程。在新老堤交界处两侧各30m(桩号3+170m~3+230m)范围内采用混凝土板护坡,板厚为12cm,混凝土垫层5cm,碎石垫层15cm,混凝土板尺寸为2m×3m。护坡底部设混凝土脚槽,底宽0.5m,顶宽1.5m,高0.5m,边坡1:1。护坡顶端设混凝土压顶,宽0.5m,高0.3m。混凝土板与土坡相接处为防止淘刷设0.5m×0.25m(高×宽)的混凝土封堵梁。混凝土强度为C20、F200。
2.3堤防稳定计算
2.3.1渗流及渗透稳定计算
1)基本资料:见表1
2)渗流计算按《堤防工程设计规范》附录E.3透水堤基均质土堤渗流计算中的(E.3.1)和(E.3.2-1)进行计算。经计算表明各段堤防均不出现逸出点。
渗透稳定计算成果表表2
3)渗透稳定分析。计算结果表明各段堤防渗透坡降小于允许坡降,渗流量很小,且背水坡地面较高,不出现流土和管涌现象。
2.3.2土堤抗滑稳定分析
根据堤防设计规范《GB50286-98》附录计算。
1)工作条件。正常情况:设计洪水位下的稳定渗流期或不稳定渗流期的背水侧堤坡,设计洪水位骤降期的临水坡。
非常情况:施工期的临水堤坡。
2)基本资料见表3。
基础材料表3
3)计算方法及采用公式。按瑞典圆弧滑动及改良圆弧法计算,计算结果见表4。
稳定分析计算成果表表4
经计算,抗滑稳定均满足要求。
3施工方案总体布置
3.1.1施工道路布置与设计
靑沟子林江堤防场外道路交通发达,土石方及其它材料、设备可通过公路和农田路输送到施工堆场和仓库,但场内需布置施工便道,便道总长2km,路宽4m。
3.1.2建筑材料堆场及临时仓库布置与设计
为保证工程施工,加强对三大材料、金属结构及机电设备等材料的保管,需在离施工场地较近的地方建设材料堆场、防雨棚、临时仓库进行储存,建临时房屋、施工仓库面积共100m2。
3.1.3施工围堰布置与设计
靠近江边修建护脚段需修建围堰进行施工导流,因本堤防工程级别是3级,按堤防设计标准堤防和围堰的度汛标准取5年一遇,顶宽2m。临水坡1:0,背水坡1:1.0,围堰采用袋装土石围堰,围堰总长160m。
3.2堤防工程施工
3.2.1施工要求
严格按原设计图纸及堤防施工规范进行施工,上坝材料要符合土工试验技术要求,压实要达到设计干容重,加强施工管理,杜绝责任事故,做到安全施工。
3.2.2施工工艺流程
根据施工图设计和有关的规范,本堤防工程采用以下施工工艺流程:堤基、堤坡清理→护脚基础开挖→混凝土护脚→回填→填筑堤料→混凝土护坡→砂袋土→石笼沉排→竣工验收。
3.2.3施工质量控制与验收标准
1)土方工程的质量控制。根据设计要求,本工程采用的筑堤土料为风化料。筑堤土的含水量控制在20%~30%之间,风化料不小于1.78t/m3,并以此为验收标准。
2)混凝土的质量控制。加强对砂、碎石、水泥的进料检查把关,包括对抵达工地的砂、碎石的含泥量进行检测,运至工地的水泥应有厂家的产品试验报告、合格证明。加强材料分类管理,水泥仓库宜设在干燥地点,按品种、标号、厂家、出厂日期分别堆放,使用前认真重新检验,认真试验选定混凝土的施工配合比,混凝土的拌合和运输应严格按《技术规范》执行,控制运输时间,加强操作人员培训,提高操作技能,以确保混凝土质量。
3)反滤层的质量控制。砂石反滤层厚度应符合设计规定,黄砂层厚度不小于10cm;碎石层厚度不小于20cm。砂石摊铺密实,厚薄均匀。
4结束语
对牡丹江干流防洪工程二期段水毁应急修复工程按批准的设计内容于2012年建设完成,通过市水利局及工程质量监督站验收合格投入使用,工程档案资料齐全,质量合格,水毁工程修复之后运行正常,已保护了沿河两岸人民群众生命财产安全,保护了沿河两岸农田,确保工程发挥最大作用。
参考文献
[1]郭辞贫;安康市农村公路路基路面材料与典型结构研究[D];长安大学;2009年
[2]卫强;公路路基高边坡整体稳定性分析研究[D];重庆交通大学;2010年
[3]张华为;公路路基填筑厚度检测的瑞雷面波方法及理论研究[D];中南大学;2012年
中小河流堤防的的安全关系到城乡居民生命财产的安危,本文以牡丹江干流防洪工程(二期)水毁修复工程为例,将已建防洪工程遭受“7.28”洪水损毁的堤段恢复重建设计,同时针对其施工难点,采取有针对性的施工措施,确保了施工质量,取得了良好的效果,为类似地质工程的堤防修复设计与施工提供了经验。
关键词:堤防水毁修复,加固设计,稳定性预算,施工要点
Abstract:Small river embankment safety relates to the urban and rural residents of life and property safety, this paper takes mudanjiang river flood control project (phase ii) waterlogging repair project as an example, the flood control works will have been built by the \"7.28\" flood damaged some reconstruction design, for its construction difficulties at the same time, targeted the construction measures, to ensure the construction quality, achieved good effect, for the similar geological engineering of dyke repair design and construction experience.
Keywords: repair damaged by flood embankment reinforcement design, budget stability, construction key points
中圖分类号: TM421;TM63 文献标识码:A
1工程概况
1.1项目概况
牡丹江干流防洪工程(二期)沿江受保护的乡镇有6个,分别是贤儒镇、红石乡、江南镇、黑石乡、靑沟子乡、大山镇,保护人口2.3万人,耕地13万亩。原设计堤防总长50.28km,回水堤长8.05km,支流规划堤防长度3.3km(西黄泥河左岸2.7km,大石河左岸0.6km),排水涵闸23座,防洪闸1座,疏通黑石电站下游河道工程。乡镇段堤防工程在遭受“7.28”大洪水后各乡镇均出现了不同程度的损毁,靑沟子林江堤防冲刷严重。
1.2原项目设计情况
1)防洪标准。敦化市牡丹江干流(靑沟子林江)堤防为牡丹江干流防洪工程的二期工程(即乡镇段),堤防防洪标准为30年一遇洪水,堤防级别为3级。排涝洪水标准为10年一遇洪水。
2)原设计洪水。靑沟子林江堤防设计洪水根据下游大山嘴子水文站按面积比的0.68次方关系确定,设计洪峰流量为2670m3/s。
3)工程任务和规模。敦化市牡丹江干流防洪工程(二期)靑沟子林江堤防原设计的主要任务是将防洪标准提高到30年一遇标准,保护总人口320人,耕地250hm2。敦化市牡丹江干流防洪工程(二期)靑沟子林江堤防原设计干流总长3.2km,回水堤1.75km,排水涵闸1座。
4)实施情况。根据设计批复文件及设计报告二期工程于2000年进行了开工建设。靑沟子林江堤防按设计完成干流3200m的土堤填筑,护坡及护脚均未完成。
2水毁修复设计方案
2.1设计原则
本次设计的原则是将已建防洪工程遭受“7.28”洪水损毁的堤段恢复重建,达到原设计标准;未按原设计修建完成在“7.28”洪水作用下造成严重损失的地段,应按原设计进行重建后达到原设计标准。因此本次牡丹江干流防洪工程(二期)靑沟子林江堤防水毁修复工程设计的堤防防洪标准及排涝洪水标准仍采用原设计标准。
2.2工程设计
2.2.1堤顶宽度及堤坡
原设计堤防横断面形式为斜坡式土堤,堤顶宽度为3.0m。堤防的临水侧边坡1:2.0,背水侧边坡1:2.5。
2.2.2干流桩号0+800m处管涌处理设计
由于管涌形成原因不详,为安全起见,因此本次设计将管涌处两侧各10m范围内(即桩号0+790m~0+810m)全部挖除后进行重新填筑,堤顶高程为原设计高程。
2.2.3干流堤脚加固设计
由于干流段3200m(桩号0+000m~3+200m)堤脚及堤坡实施时并未按原设计及批复标准完成,遭受“7.28”洪水淘刷后堤脚坍塌严重,近乎垂直坡度,为了确保堤防安全,本次设计将干流段堤脚进行加固处理。加固措施采取石笼沉排护脚,护脚顶高程根据石笼厚30cm。为了使石笼沉排护脚更加稳固,并且此段为水下作业,因此先抛投砂袋土堆成1:2.5的坡后在其上放石笼。护脚顶高程为实际地面高程,为确保堤脚稳固,在护脚顶部设2.0m的石笼平台;护脚底高程为河底线,石笼沿河底水平延伸3.0m。
2.2.4回水堤恢复重建设计
在“7.28”洪水作用下民筑回水堤发生决口100m(桩号3+200m~3+300m),本次设计将决口段堤基的覆盖层清除0.5m左右后重新填筑,堤顶高程达到原设计顶高程。在新老堤交界处两侧各30m(桩号3+170m~3+230m)范围内采用混凝土板护坡,板厚为12cm,混凝土垫层5cm,碎石垫层15cm,混凝土板尺寸为2m×3m。护坡底部设混凝土脚槽,底宽0.5m,顶宽1.5m,高0.5m,边坡1:1。护坡顶端设混凝土压顶,宽0.5m,高0.3m。混凝土板与土坡相接处为防止淘刷设0.5m×0.25m(高×宽)的混凝土封堵梁。混凝土强度为C20、F200。
2.3堤防稳定计算
2.3.1渗流及渗透稳定计算
1)基本资料:见表1
2)渗流计算按《堤防工程设计规范》附录E.3透水堤基均质土堤渗流计算中的(E.3.1)和(E.3.2-1)进行计算。经计算表明各段堤防均不出现逸出点。
渗透稳定计算成果表表2
3)渗透稳定分析。计算结果表明各段堤防渗透坡降小于允许坡降,渗流量很小,且背水坡地面较高,不出现流土和管涌现象。
2.3.2土堤抗滑稳定分析
根据堤防设计规范《GB50286-98》附录计算。
1)工作条件。正常情况:设计洪水位下的稳定渗流期或不稳定渗流期的背水侧堤坡,设计洪水位骤降期的临水坡。
非常情况:施工期的临水堤坡。
2)基本资料见表3。
基础材料表3
3)计算方法及采用公式。按瑞典圆弧滑动及改良圆弧法计算,计算结果见表4。
稳定分析计算成果表表4
经计算,抗滑稳定均满足要求。
3施工方案总体布置
3.1.1施工道路布置与设计
靑沟子林江堤防场外道路交通发达,土石方及其它材料、设备可通过公路和农田路输送到施工堆场和仓库,但场内需布置施工便道,便道总长2km,路宽4m。
3.1.2建筑材料堆场及临时仓库布置与设计
为保证工程施工,加强对三大材料、金属结构及机电设备等材料的保管,需在离施工场地较近的地方建设材料堆场、防雨棚、临时仓库进行储存,建临时房屋、施工仓库面积共100m2。
3.1.3施工围堰布置与设计
靠近江边修建护脚段需修建围堰进行施工导流,因本堤防工程级别是3级,按堤防设计标准堤防和围堰的度汛标准取5年一遇,顶宽2m。临水坡1:0,背水坡1:1.0,围堰采用袋装土石围堰,围堰总长160m。
3.2堤防工程施工
3.2.1施工要求
严格按原设计图纸及堤防施工规范进行施工,上坝材料要符合土工试验技术要求,压实要达到设计干容重,加强施工管理,杜绝责任事故,做到安全施工。
3.2.2施工工艺流程
根据施工图设计和有关的规范,本堤防工程采用以下施工工艺流程:堤基、堤坡清理→护脚基础开挖→混凝土护脚→回填→填筑堤料→混凝土护坡→砂袋土→石笼沉排→竣工验收。
3.2.3施工质量控制与验收标准
1)土方工程的质量控制。根据设计要求,本工程采用的筑堤土料为风化料。筑堤土的含水量控制在20%~30%之间,风化料不小于1.78t/m3,并以此为验收标准。
2)混凝土的质量控制。加强对砂、碎石、水泥的进料检查把关,包括对抵达工地的砂、碎石的含泥量进行检测,运至工地的水泥应有厂家的产品试验报告、合格证明。加强材料分类管理,水泥仓库宜设在干燥地点,按品种、标号、厂家、出厂日期分别堆放,使用前认真重新检验,认真试验选定混凝土的施工配合比,混凝土的拌合和运输应严格按《技术规范》执行,控制运输时间,加强操作人员培训,提高操作技能,以确保混凝土质量。
3)反滤层的质量控制。砂石反滤层厚度应符合设计规定,黄砂层厚度不小于10cm;碎石层厚度不小于20cm。砂石摊铺密实,厚薄均匀。
4结束语
对牡丹江干流防洪工程二期段水毁应急修复工程按批准的设计内容于2012年建设完成,通过市水利局及工程质量监督站验收合格投入使用,工程档案资料齐全,质量合格,水毁工程修复之后运行正常,已保护了沿河两岸人民群众生命财产安全,保护了沿河两岸农田,确保工程发挥最大作用。
参考文献
[1]郭辞贫;安康市农村公路路基路面材料与典型结构研究[D];长安大学;2009年
[2]卫强;公路路基高边坡整体稳定性分析研究[D];重庆交通大学;2010年
[3]张华为;公路路基填筑厚度检测的瑞雷面波方法及理论研究[D];中南大学;2012年