大同第二发电厂电除尘器改造前 ,除尘效率不足 96 % ,烟尘排放浓度大 ,不能满足环境保护和吸风机安全运行的要求。为了提高除尘效率 ,该电厂分别对 1 ,2 ,3,5号炉电除尘器进行了改造。改造时 ,拆除原有电除尘器的阴、阳极系统 ;加高电场并沿烟气流动方向延长电场 ;调宽极距 ,使电除尘器收尘面积增大 ;更新电除尘器控制系统 ;改造原变压器后继续使用。电除尘器改造后 ,电除尘效率大于 99.6 % ,烟尘排放浓度小于 1 0 0mg/m3 ,达到了设计要求
Datong Second Power Plant ESP before transformation, less than 96% efficiency of dust removal, dust emission concentration, can not meet the requirements of environmental protection and safe operation of suction fan. In order to improve the efficiency of dust removal, the power plant respectively 1, 2, 3, 5 electric precipitator was modified. During the transformation, the negative and anodic systems of the original electrostatic precipitator were removed; the electric field was increased and the electric field was extended along the flue gas flow; the pole pitch was widened to increase the dust collecting area of the electrostatic precipitator; the control system of the electrostatic precipitator was renewed; The original transformer continue to use. After the electric dust remodeling, the ESP efficiency is more than 99.6% and the smoke and dust emission concentration is less than 100mg / m3, which meets the design requirements