双柏县(石咢)加地区具有丰富的水力资源,是我州电力规划中的能源开发基地。在此地区,共规划了16座电站,装机容量共计7万多千瓦。1991年1月10日,规划中的第一座电站——双柏鱼庄河电站,正式破土动工。该电站装机为2×1600千瓦,通过长50公里的35千伏送电线路并入地区电网,电站投资共736万元(不含送电线路)。这个电站的建成,一方面将供给(石咢)加地区及双柏县工农业用电的需要,同时,也为其它电站今后的不断开发打下了良好的基础。电站的勘测设计由楚雄州水电设计处承担,能源部第十四工程局四公司承担施工。
Shuangbai County (Shijie) plus the region has a wealth of water resources, power planning in my state’s energy development base. In this area, a total of 16 power plants have been planned with installed capacity of more than 70,000 kilowatts. January 10, 1991, the planning of the first power station - Shuangbaoyuzhuanghe power station, officially broke ground. The power plant installed capacity of 2 × 1600 kilowatts, through the 50 kilometer long 35 kV transmission lines into the regional power grid, power station total investment 7.36 million yuan (excluding transmission lines). The completion of this power station will not only supply the needs of both industrial and agricultural electricity sources in Shibao and Shuangbai County but also lay a good foundation for the continuous development of other power plants in the future. Survey and design of the power station by the Chuxiong Hydropower Design Office, Department of Energy 14th Engineering Bureau of four companies to undertake the construction.