由于湖北电力系统目前存在着供电与用电、火电用煤与煤炭供应矛盾,随着负荷的发展和电力结构变化,负荷峰谷越来越大,根据系统特点及调峰要求,兴建隔河岩大型水电站是必要而有利的。从电力系统调峰、配合葛洲坝水电站运行、发电量、与已建大型水电站比较、电力系统经济效益等方面分析,隔河岩水电站装机容量120万kW是经济合理的。
Due to the current power supply and electricity consumption in Hubei power system, there is a contradiction between thermal power coal supply and coal supply. With the development of load and the change of power structure, the load peak-valley becomes larger and larger. According to the characteristics of the system and the requirements of peak regulation, Large hydropower station is necessary and favorable. From the peaking of the power system, with the operation of Gezhouba Hydropower Station, generating capacity, comparison with the existing large-scale hydropower stations, and the economic benefits of the power system, the installed capacity of Geheba Hydropower Station is economically reasonable.