2013年是串列升级工程建设中的关键之年,攻坚之年。在这一年里,串列加速器升级工程部(以下简称工程部)在国防科工局、集团公司、院领导的亲切关怀指导下,在院各职能处室及串列加速器升级工程各参建单位的大力支持下,全体职工理清工作思路,齐心协力,共同努力,在建筑施工、主工艺设备安装、调试均取得了重大进展,圆满完成了全年的各项任务。1建筑工程实现四方验收,公用工程设备完成安装并投入使用2013年,土建工程完成了施工合同规定应有的建设内容,于2013年7月通过了四方验收。工
2013 is a key year in the construction of serial upgrading project, and a crucial year for tackling this problem. During this year, the Tandem Accelerator Upgrade Engineering Department (hereinafter referred to as the Engineering Department), under the guidance and guidance of the leaders of the National Defense Bureau, the Group Corporation and the Institute, With the strong support from the units, all staffs worked out the work train of thought, made concerted efforts and worked together to make great progress in the construction and installation of main process equipment and debugging, and successfully completed all the tasks of the year. 1 Four-party acceptance of construction projects, completion of installation and commissioning of utility equipment In 2013, civil works completed the construction content stipulated in the construction contract and passed the inspection and acceptance of the Quartet in July 2013. work