The design and install of ground floor wall and pillar template engineering
【Abstract】 Only there is design and install firm, dependable with template of the gearing and put together to sew tight, can resist the
concrete self-respect with construction carry, operating the personnel can proceed every kind of construction homework successfully,
then can insure the construction quantity and safety, eradicate completely the template leak syrup, bulge mold etc. quantity common
failing, then can make ground floor wall pillar that sprinkle built to guarantee both quality and quantity ground attaining to accept heavy
with round, watertightness blocks up to leak and good clear water impressions.
【Key words】 Ground floor;Wall;Pillar;Template engineering;Design;Install
1概述
地下室墙柱既有承重与围护功能,又有严格的防水堵漏功能,同时对于作为地下车库或者设备房的地下室,为了节省造价,往往没有不再做装修粉刷,利用墙柱的清水墙面。因此,相对上部结构来说,地下室墙柱的施工有更为严格的要求。对于现浇钢筋混凝土墙柱的施工质量效果,不仅取决于混凝土配合比与浇灌方法,而且在很大程度上取决于采用的支架及模板质量。为了达到地下室墙柱得以上功能,确保施工质量,认真对其模板工程进行严格的设计与施工,是一项重要的任务。只有设计与安装的模板牢固、可靠、拼缝严密,能抵抗混凝土自重和施工荷载,操作人员能顺利地进行各种施工作业,才能确保施工质量和安全,杜绝模板漏浆、胀模等质量通病,才能使浇筑的地下室墙柱保质保量地达到承重与围护、防水堵漏和良好的清水观感。
某工程建设用地面积23968.8m2,地上6层,建筑面积59905.3m2,地下室1层,建筑面积15399.9m2。结构采用框剪结构体系(柱网以14×12m为主),天然地基,地下室地下室层高5.1m。该工程地下室底板、顶板、外墙及与土壤接触的构件,都采用集料级配的防水混凝土,掺混凝土膨胀防水剂,混凝土强度等级C50、抗渗等级S8。现对施工过程中,我们对该地下室墙柱模板工程的设计与施工作本文的介绍。
2模板设计
2.1该工程地下室底板厚800mm,墙下条形基础边缘为墙边加500mm,我们设计采用18厚夹板配@500的80×80木枋作底板模板,设计如图1。
2.2地下室外墙厚300mm、内剪力墙厚20mm,该工程地下室钢筋混凝土墙柱也采用18厚夹板配木枋和拉杆作模板,设计如图2、3。
2.3矩形柱截面有300×300mm、300×600mm、300×900mm与300~1200mm,还有部分异型柱,模板设计分一般矩形柱(300×300mm、300×600mm)、大截面柱(300×900mm、300~1200mm)与异型柱3种,分别见图4、5、6。
2.4地下室楼梯踏步定型模板采用钢模,按照楼梯的宽度、高度和长度,踏步的步数来配制。采用12厚竹胶板做底模,底模施工完后,绑扎钢筋。钢筋绑好后,把踏步定型钢模吊入梯段上部固定,做法见图7。
3模板安装
模板安装前要做好模板的定位基准工作,其工作有:①进行中心线和位置的放线,首先由控制线引测建筑物的柱或墙轴线,并以该轴线为起点引测建筑物边线以及模板控制线;②做好标高测量工作,用水准仪把建筑水平标高根据实际标高的要求直接引测到模板安装位置;③模板支承垫底部应预先找平,以保证模板位置正确,防止模板底部漏浆,即沿模板边线用1:3水泥砂浆抹找平层,宽度为50mm;④所用模板要涂刷脱模剂。
模板开料必须符合结构尺寸,安装前在结构墙柱的地面位置按弹出的墨线用钢钉安装固定墙柱模板位,其位置要注意预留墙柱木模板的厚度,用于固定柱模板的位置,起到柱箍及墙固定点作用。
墙柱模板施工时,如小型柱先安装加强块板侧板,紧接着安装侧面板,最后安装加强板。一般大截面的柱先安装各侧模板,后安装各边加强木枋,再安装水平木枋;大截面柱及剪力墙模板先安装各边模板后,采用对拉螺杆收紧的施工方法安装。
对于地下室外墙,由于有严格的混凝土自防水要求,在施工缝上要求做认真的节点处理,如图8所示。同时地下室外墙所有模板对拉螺杆要求在中间焊接钢板止水环处理,如图9所示。
在模板施工时,随着墙柱各侧夹板安装,应用铁钉上中下进行固定。固定后用60×80mm或80×80mm的木枋或Φ48双钢管作初步固定。初步固定后,安装斜支撑(宜45°),对墙柱模板进行垂直校正。在垂直校正过程中,应边校正边用斜支撑进行垂直位固定。柱两个垂直面固定好后,立即对柱模板进行最后工序加固,加固定后应再次对模板垂直度校正,固定斜撑也应作相应的调整。
在混凝土浇筑完毕后,为防止砼在浇筑施工过程中,对模板的冲击所产生的移位,所以应重新对墙柱的垂直度进行校正,确保墙柱施工质量。
由于模板在施工中加固及钻孔等多种原因,使墙柱头的位置积聚木屑等垃圾。为配合及保证新砼与旧砼在墙柱头接触位的质量,模板施工时在墙柱头附近的一侧模板开一个100×100mm的小孔,用于清理垃圾用,浇砼时随即封口。
混凝土强度能保证拆模时墙柱表面及棱角不受损时,方可拆除模板。拆除时,先拆掉墙柱模板的拉杆(或支撑),再拆除墙柱箍,然后用撬杠轻轻撬动模板,使模板与混凝土脱离。模板拆除后,应及时搬走或堆放好,为下一道工序预留工作面。
4结语
对于地下室墙柱模板工程,可靠和牢固的设计是施工成功的前提,而认真按图施工安装则是实现设计目的的有效途径。我们在该工程的施工过程中,对该地下室墙柱的模板工程进行严格认真的设计与安装,达到了该地下室墙柱的承重与围护、防水堵漏和良好的清水观感功能。该工程地下室墙柱模板工程的设计与安装方法,希望能为其它同类工程提供有益的参考。
参考文献
1孙训方等.材料力学.第一版.高等教育出版社,1979.7
2杨嗣信主编.高层建筑施工手册.第一版.中国建筑工业出版社,
1992.12
【关键词】 地下室;墙;柱;模板工程;设计;安装
【中图分类号】 TU225 【文献标识码】 A【文章编号】 1727-5123(2010)02-038-03
The design and install of ground floor wall and pillar template engineering
【Abstract】 Only there is design and install firm, dependable with template of the gearing and put together to sew tight, can resist the
concrete self-respect with construction carry, operating the personnel can proceed every kind of construction homework successfully,
then can insure the construction quantity and safety, eradicate completely the template leak syrup, bulge mold etc. quantity common
failing, then can make ground floor wall pillar that sprinkle built to guarantee both quality and quantity ground attaining to accept heavy
with round, watertightness blocks up to leak and good clear water impressions.
【Key words】 Ground floor;Wall;Pillar;Template engineering;Design;Install
1概述
地下室墙柱既有承重与围护功能,又有严格的防水堵漏功能,同时对于作为地下车库或者设备房的地下室,为了节省造价,往往没有不再做装修粉刷,利用墙柱的清水墙面。因此,相对上部结构来说,地下室墙柱的施工有更为严格的要求。对于现浇钢筋混凝土墙柱的施工质量效果,不仅取决于混凝土配合比与浇灌方法,而且在很大程度上取决于采用的支架及模板质量。为了达到地下室墙柱得以上功能,确保施工质量,认真对其模板工程进行严格的设计与施工,是一项重要的任务。只有设计与安装的模板牢固、可靠、拼缝严密,能抵抗混凝土自重和施工荷载,操作人员能顺利地进行各种施工作业,才能确保施工质量和安全,杜绝模板漏浆、胀模等质量通病,才能使浇筑的地下室墙柱保质保量地达到承重与围护、防水堵漏和良好的清水观感。
某工程建设用地面积23968.8m2,地上6层,建筑面积59905.3m2,地下室1层,建筑面积15399.9m2。结构采用框剪结构体系(柱网以14×12m为主),天然地基,地下室地下室层高5.1m。该工程地下室底板、顶板、外墙及与土壤接触的构件,都采用集料级配的防水混凝土,掺混凝土膨胀防水剂,混凝土强度等级C50、抗渗等级S8。现对施工过程中,我们对该地下室墙柱模板工程的设计与施工作本文的介绍。
2模板设计
2.1该工程地下室底板厚800mm,墙下条形基础边缘为墙边加500mm,我们设计采用18厚夹板配@500的80×80木枋作底板模板,设计如图1。
2.2地下室外墙厚300mm、内剪力墙厚20mm,该工程地下室钢筋混凝土墙柱也采用18厚夹板配木枋和拉杆作模板,设计如图2、3。
2.3矩形柱截面有300×300mm、300×600mm、300×900mm与300~1200mm,还有部分异型柱,模板设计分一般矩形柱(300×300mm、300×600mm)、大截面柱(300×900mm、300~1200mm)与异型柱3种,分别见图4、5、6。
2.4地下室楼梯踏步定型模板采用钢模,按照楼梯的宽度、高度和长度,踏步的步数来配制。采用12厚竹胶板做底模,底模施工完后,绑扎钢筋。钢筋绑好后,把踏步定型钢模吊入梯段上部固定,做法见图7。
3模板安装
模板安装前要做好模板的定位基准工作,其工作有:①进行中心线和位置的放线,首先由控制线引测建筑物的柱或墙轴线,并以该轴线为起点引测建筑物边线以及模板控制线;②做好标高测量工作,用水准仪把建筑水平标高根据实际标高的要求直接引测到模板安装位置;③模板支承垫底部应预先找平,以保证模板位置正确,防止模板底部漏浆,即沿模板边线用1:3水泥砂浆抹找平层,宽度为50mm;④所用模板要涂刷脱模剂。
模板开料必须符合结构尺寸,安装前在结构墙柱的地面位置按弹出的墨线用钢钉安装固定墙柱模板位,其位置要注意预留墙柱木模板的厚度,用于固定柱模板的位置,起到柱箍及墙固定点作用。
墙柱模板施工时,如小型柱先安装加强块板侧板,紧接着安装侧面板,最后安装加强板。一般大截面的柱先安装各侧模板,后安装各边加强木枋,再安装水平木枋;大截面柱及剪力墙模板先安装各边模板后,采用对拉螺杆收紧的施工方法安装。
对于地下室外墙,由于有严格的混凝土自防水要求,在施工缝上要求做认真的节点处理,如图8所示。同时地下室外墙所有模板对拉螺杆要求在中间焊接钢板止水环处理,如图9所示。
在模板施工时,随着墙柱各侧夹板安装,应用铁钉上中下进行固定。固定后用60×80mm或80×80mm的木枋或Φ48双钢管作初步固定。初步固定后,安装斜支撑(宜45°),对墙柱模板进行垂直校正。在垂直校正过程中,应边校正边用斜支撑进行垂直位固定。柱两个垂直面固定好后,立即对柱模板进行最后工序加固,加固定后应再次对模板垂直度校正,固定斜撑也应作相应的调整。
在混凝土浇筑完毕后,为防止砼在浇筑施工过程中,对模板的冲击所产生的移位,所以应重新对墙柱的垂直度进行校正,确保墙柱施工质量。
由于模板在施工中加固及钻孔等多种原因,使墙柱头的位置积聚木屑等垃圾。为配合及保证新砼与旧砼在墙柱头接触位的质量,模板施工时在墙柱头附近的一侧模板开一个100×100mm的小孔,用于清理垃圾用,浇砼时随即封口。
混凝土强度能保证拆模时墙柱表面及棱角不受损时,方可拆除模板。拆除时,先拆掉墙柱模板的拉杆(或支撑),再拆除墙柱箍,然后用撬杠轻轻撬动模板,使模板与混凝土脱离。模板拆除后,应及时搬走或堆放好,为下一道工序预留工作面。
4结语
对于地下室墙柱模板工程,可靠和牢固的设计是施工成功的前提,而认真按图施工安装则是实现设计目的的有效途径。我们在该工程的施工过程中,对该地下室墙柱的模板工程进行严格认真的设计与安装,达到了该地下室墙柱的承重与围护、防水堵漏和良好的清水观感功能。该工程地下室墙柱模板工程的设计与安装方法,希望能为其它同类工程提供有益的参考。