摘要:随着我国经济发展速度不断加快,人们生活质量不断改善,对于房屋建筑质量的要求也随之不断提高。建筑防水工程对于房屋建筑整体质量具有十分重要的影响,一旦出现问题,往往会导致建筑发生渗漏,严重影响用户的正常使用。本文在此对常见的“四漏”问题的质量控制做了逐一分析,并在最后提出了防水工程的具体应对技术。
关键词:防水;质量控制;处理技术
Abstract: As China's accelerating economic development, people's quality of life continues to improve, the quality of housing construction requirements also continue to improve. Building waterproof engineering has very important influence on the overall quality of housing construction, once appear problem, often leaks in the building, seriously affect the normal use of the user. Based on the common "four leakage" problem of quality control was analyzed one by one, and finally puts forward concrete technology with waterproof engineering.
Key words: waterproofing; quality control; processing technology
中圖分类号:TUT12+3 文献标识码:文章编号:
地下工程防水质量控制民用地下防水工程的质量管理应该遵循《地下防水技术规范》进行实施,比如说住宅建筑地下工程中导墙以下部分需要进行防水处理,其防水层与建筑的主体结构应该采用建筑空粘法。建筑结构中的底板垫层混凝土一般采用空铺法、点粘法、条粘法和机械固定法,但是为了能够更好的控制地下工程防水,空铺法较为合适,在搭建防水卷材过程应该认真仔细,如果搭建部分没有做好细节处理,粘接的不牢靠,在以后往往会出现地下渗水现象。地下防水卷材应该严格把关,在搭建过程中,其长短边的搭建应该控制在90mm~100mm之间,为了防止出现空鼓现象,其防水卷材的封边过程需要排空渗入的空气,封边位置需要挤出热熔沥青。地下工程中底板的防水的施工过程首先是利用防水导墙将卷材引导到高度为1m左右的位置,在引导过程中,防水导墙的堆砌应该采用240mm的实心砖进行建筑,其高度应该控制在900mm。处于导墙顶部并且靠近结构墙面阳角部位的防水卷材容易遭到混凝土浇灌破坏以及支模破坏,所以在这部分防水卷材的搭建后,需要在其上面搭建两片空砖,做好防护措施,当底板和地下室外墙面施工完成后,应当及时去掉这两片空砖。内部细节处理完成后,才应该进行室外大面积防水卷材铺设作业。地下工程墙面部分的防水作业处理,地下墙面的防水控制应该注重墙面与防水卷材的粘度控制,在墙面防水卷材的施工过程中,应该采用满粘贴方式,这样可以有效的防止在粘贴完卷材后,由于其内部有空气空隙的存在而导致卷材脱落或者是渗水现象。二、屋面工程防水质量控制建筑屋面可采用正置式、倒置式进行防水,以下主要对倒置式防水进行分析,对防水施工过程中的质量控制措施进行分析。1、找平层分格缝的防水处理
屋面找平层容易开裂,为了对其进行防止,需要将分格缝设置在找平层上,因此,将一层200mm宽的防水卷材铺在分格缝上,继而作为防水层。2、对水落口防水施工控制
为了防止遇到暴雨时产生倒水现象,因此,先用密封材料将水落口与竖管承插口的连接处进行嵌填密实。水落口可以分为直落式和墙排式,但是无论是哪种形式都应在周围500mm内做防水附加层。3、出屋面金属管道防水收口处理
此处理主要采用40×3扁钢箍包紧防水卷后,再用螺丝拧紧。在施工过程中,应该把对金属管箍与防水卷材的牢固程度进行重点检查。4、屋面女儿墙压预防水施工控制
在屋面女儿墙位置进行外墙保温时,很容易产生裂缝,如果处理不好此裂缝,那么就会导致水流至墙体内部,从而使得墙体或者窗口渗水。因此,需要进行压顶,在女儿墙上进行,等到完成压顶后,在上面涂上防水涂料(水泥基)。 三、卫生间防水质量控制1、在卫生间的门槛部位设置混凝土门槛,其高度一般控制在75mm左右,其宽度与墙面宽度保持一致,为了协同地暖管,应该在其上设置两个适当的凹槽,以供其地暖使用。2、在施工过程中应该门槛部分的防水施工应该先做好阴角与凹槽处圆角,完成后需要在其表面粉刷防水涂料。卫生间门槛完成后,将防水搭接至门槛上,使其形成闭合的防水层。除此之外还应该处理好卫生间内出地面管道的防水措施处理,一般的做法是在涂刷完毕的防水管道上做加强处理,首先在做好防水一级处理的管道上铺设帆布,防止管道破裂,然后再次做防水加强层。
四、防水工程的具体处理技术
1、水落口、地漏、过水孔
这些部位处在两种材料交接处,由于混凝土和砂浆千缩和两种材料的胀缩不同,会使这些部位的周边产生裂缝。另外它也是雨水集中且容易积水的部位,而且所处位置工作面狭小,施工工序叉多,施工质量难以保证。根据节点设防原则,应进行多道设防和节点密封处理,所以在水落口、漏斗和套管的周边,预留10mm。
2、防水层收头
柔性防水层的末端收头处,由于防水层的收缩,再经雨水和风力作用,常常提前翘边、脱层,在大面防水层之前渗漏。因此在卷材收头处必须用压条钉压固定,再用密封材料封口;在砖泛水处预留凹槽,收头压人槽中,再用水泥砂浆保护;混凝土泛水处理,收头上部要用卷材或金属覆盖保护;涂膜的收头,则应分层错开,不可集中于一处。
3、屋面天沟檐口
这些部位不但容易变形,而且受雨水严重冲刷,沟中也常常因长期积水、干湿交替而对防水造成严重破坏。很多工程的防水层,首先是沟中或沟沿防水层提早失效而发生渗漏,因此应在这些部位作增强层。由于平面多变,施工工作面小的原因,采用卷材是很不利的,宜采用涂膜防水予以配套。一般都作涂膜增强,有一布三涂和二布四涂作法,即在天沟交角处或者整个天沟和檐口先涂涂料,再铺增强胎体,再涂涂料1~2mm厚;在檐口处,构件断面形状复杂,可采取增强空铺层处理,或先涂隔离剂或压敏型抗裂胶后再作增强层。
4、压顶
压顶处于屋面的最高处,直接暴露于自然环境中,受气候影响大,受整个纵向墙体温差、结构受力变形及墙体混凝土与砂浆干缩变形的影响也很大,因此即使是配筋混凝土压顶,其横向裂缝也是不可避免的。一般在3—5年内裂缝均会明显地开展,配筋混凝土压顶,在5~8m之内就会有1条裂缝开展,不配筋混凝土在1m左右就有1条裂缝。雨水顺裂缝到墙内,绕过防水层漏到室内,所以压顶必须作柔性材料增强层。一般是作在压顶下,如果选材不当,可能会造成压顶与女儿墙分层,目前只有聚合物水泥基涂料和聚合物水泥砂浆可以用于此处防水;另一种是将防水层作在压顶上面,采取卷材粘贴或用涂料涂刷。
5、阴阳角
屋面的平面与立面交角处、地下室底面与墙面内外交角处、檐口与天沟交接处、天沟转角处、两个立面转角处形成阴阳角。这些部位常由于混凝土、砂浆干缩和温差变形产生应力集中导致开裂,有些裂缝宽度可扩展到5mm。阴阳角的增强层可采用卷材条,即在交角处铺贴1层100~150mm宽的卷材条予以加强。但由于卷材较硬挺,在交角处难以铺平、铺实,往往采用涂料加增强胎体布作为增强层,即在交角处涂150—200mm宽、厚1~2mm的加胎体的涂层。胎体铺贴时切忌拉紧,应松弛不皱。
6、板端缝
屋面、楼板支承端的板缝称板端缝。不管是现浇还是装配结构板,由于荷载作用产生板端负弯矩,板面下挠而板端上部裂开,再加上混凝土、砂浆的干缩和温差变形的影响,会使板端产生较大的板端裂缝。因此,板端缝的增强层应有较强的适应基层变形的能力,可采用以下方法处理:
①卷材增强层。采用卷材作增强层应采取空铺的方法。可采用200~300mm宽、1.2mm厚的高分子卷材或3mm厚改性沥青卷材单边点粘在板端处,或用压敏型粘结剂,然后铺贴大面积防水层。
②涂膜增强层。采用加胎体的防水涂料作增强层,涂料可采用与大面积防水层相容的高分子涂料或聚合物改性沥青涂料。其作法是,在板端缝处200—300mm宽范围先涂刷隔离层150~250mm(如石灰水、石蜡或压敏型抗裂胶),干燥后逐层涂刷防水涂料,铺设胎体,一般一布三涂或二布四涂,然后再施工大面积防水层。
参考文献:
【1】GB 50108-2008.地下工程防水技术规范[S].
【2】张云霞,刘琳,赵荣香. 建筑物防水施工的要点[J].山西建筑, 2007,(05).【3】建筑施工手册(第四版)[M].北京:中国建筑工业出版社,2003.
关键词:防水;质量控制;处理技术
Abstract: As China's accelerating economic development, people's quality of life continues to improve, the quality of housing construction requirements also continue to improve. Building waterproof engineering has very important influence on the overall quality of housing construction, once appear problem, often leaks in the building, seriously affect the normal use of the user. Based on the common "four leakage" problem of quality control was analyzed one by one, and finally puts forward concrete technology with waterproof engineering.
Key words: waterproofing; quality control; processing technology
中圖分类号:TUT12+3 文献标识码:文章编号:
地下工程防水质量控制民用地下防水工程的质量管理应该遵循《地下防水技术规范》进行实施,比如说住宅建筑地下工程中导墙以下部分需要进行防水处理,其防水层与建筑的主体结构应该采用建筑空粘法。建筑结构中的底板垫层混凝土一般采用空铺法、点粘法、条粘法和机械固定法,但是为了能够更好的控制地下工程防水,空铺法较为合适,在搭建防水卷材过程应该认真仔细,如果搭建部分没有做好细节处理,粘接的不牢靠,在以后往往会出现地下渗水现象。地下防水卷材应该严格把关,在搭建过程中,其长短边的搭建应该控制在90mm~100mm之间,为了防止出现空鼓现象,其防水卷材的封边过程需要排空渗入的空气,封边位置需要挤出热熔沥青。地下工程中底板的防水的施工过程首先是利用防水导墙将卷材引导到高度为1m左右的位置,在引导过程中,防水导墙的堆砌应该采用240mm的实心砖进行建筑,其高度应该控制在900mm。处于导墙顶部并且靠近结构墙面阳角部位的防水卷材容易遭到混凝土浇灌破坏以及支模破坏,所以在这部分防水卷材的搭建后,需要在其上面搭建两片空砖,做好防护措施,当底板和地下室外墙面施工完成后,应当及时去掉这两片空砖。内部细节处理完成后,才应该进行室外大面积防水卷材铺设作业。地下工程墙面部分的防水作业处理,地下墙面的防水控制应该注重墙面与防水卷材的粘度控制,在墙面防水卷材的施工过程中,应该采用满粘贴方式,这样可以有效的防止在粘贴完卷材后,由于其内部有空气空隙的存在而导致卷材脱落或者是渗水现象。二、屋面工程防水质量控制建筑屋面可采用正置式、倒置式进行防水,以下主要对倒置式防水进行分析,对防水施工过程中的质量控制措施进行分析。1、找平层分格缝的防水处理
屋面找平层容易开裂,为了对其进行防止,需要将分格缝设置在找平层上,因此,将一层200mm宽的防水卷材铺在分格缝上,继而作为防水层。2、对水落口防水施工控制
为了防止遇到暴雨时产生倒水现象,因此,先用密封材料将水落口与竖管承插口的连接处进行嵌填密实。水落口可以分为直落式和墙排式,但是无论是哪种形式都应在周围500mm内做防水附加层。3、出屋面金属管道防水收口处理
此处理主要采用40×3扁钢箍包紧防水卷后,再用螺丝拧紧。在施工过程中,应该把对金属管箍与防水卷材的牢固程度进行重点检查。4、屋面女儿墙压预防水施工控制
在屋面女儿墙位置进行外墙保温时,很容易产生裂缝,如果处理不好此裂缝,那么就会导致水流至墙体内部,从而使得墙体或者窗口渗水。因此,需要进行压顶,在女儿墙上进行,等到完成压顶后,在上面涂上防水涂料(水泥基)。 三、卫生间防水质量控制1、在卫生间的门槛部位设置混凝土门槛,其高度一般控制在75mm左右,其宽度与墙面宽度保持一致,为了协同地暖管,应该在其上设置两个适当的凹槽,以供其地暖使用。2、在施工过程中应该门槛部分的防水施工应该先做好阴角与凹槽处圆角,完成后需要在其表面粉刷防水涂料。卫生间门槛完成后,将防水搭接至门槛上,使其形成闭合的防水层。除此之外还应该处理好卫生间内出地面管道的防水措施处理,一般的做法是在涂刷完毕的防水管道上做加强处理,首先在做好防水一级处理的管道上铺设帆布,防止管道破裂,然后再次做防水加强层。
四、防水工程的具体处理技术
1、水落口、地漏、过水孔
这些部位处在两种材料交接处,由于混凝土和砂浆千缩和两种材料的胀缩不同,会使这些部位的周边产生裂缝。另外它也是雨水集中且容易积水的部位,而且所处位置工作面狭小,施工工序叉多,施工质量难以保证。根据节点设防原则,应进行多道设防和节点密封处理,所以在水落口、漏斗和套管的周边,预留10mm。
2、防水层收头
柔性防水层的末端收头处,由于防水层的收缩,再经雨水和风力作用,常常提前翘边、脱层,在大面防水层之前渗漏。因此在卷材收头处必须用压条钉压固定,再用密封材料封口;在砖泛水处预留凹槽,收头压人槽中,再用水泥砂浆保护;混凝土泛水处理,收头上部要用卷材或金属覆盖保护;涂膜的收头,则应分层错开,不可集中于一处。
3、屋面天沟檐口
这些部位不但容易变形,而且受雨水严重冲刷,沟中也常常因长期积水、干湿交替而对防水造成严重破坏。很多工程的防水层,首先是沟中或沟沿防水层提早失效而发生渗漏,因此应在这些部位作增强层。由于平面多变,施工工作面小的原因,采用卷材是很不利的,宜采用涂膜防水予以配套。一般都作涂膜增强,有一布三涂和二布四涂作法,即在天沟交角处或者整个天沟和檐口先涂涂料,再铺增强胎体,再涂涂料1~2mm厚;在檐口处,构件断面形状复杂,可采取增强空铺层处理,或先涂隔离剂或压敏型抗裂胶后再作增强层。
4、压顶
压顶处于屋面的最高处,直接暴露于自然环境中,受气候影响大,受整个纵向墙体温差、结构受力变形及墙体混凝土与砂浆干缩变形的影响也很大,因此即使是配筋混凝土压顶,其横向裂缝也是不可避免的。一般在3—5年内裂缝均会明显地开展,配筋混凝土压顶,在5~8m之内就会有1条裂缝开展,不配筋混凝土在1m左右就有1条裂缝。雨水顺裂缝到墙内,绕过防水层漏到室内,所以压顶必须作柔性材料增强层。一般是作在压顶下,如果选材不当,可能会造成压顶与女儿墙分层,目前只有聚合物水泥基涂料和聚合物水泥砂浆可以用于此处防水;另一种是将防水层作在压顶上面,采取卷材粘贴或用涂料涂刷。
5、阴阳角
屋面的平面与立面交角处、地下室底面与墙面内外交角处、檐口与天沟交接处、天沟转角处、两个立面转角处形成阴阳角。这些部位常由于混凝土、砂浆干缩和温差变形产生应力集中导致开裂,有些裂缝宽度可扩展到5mm。阴阳角的增强层可采用卷材条,即在交角处铺贴1层100~150mm宽的卷材条予以加强。但由于卷材较硬挺,在交角处难以铺平、铺实,往往采用涂料加增强胎体布作为增强层,即在交角处涂150—200mm宽、厚1~2mm的加胎体的涂层。胎体铺贴时切忌拉紧,应松弛不皱。
6、板端缝
屋面、楼板支承端的板缝称板端缝。不管是现浇还是装配结构板,由于荷载作用产生板端负弯矩,板面下挠而板端上部裂开,再加上混凝土、砂浆的干缩和温差变形的影响,会使板端产生较大的板端裂缝。因此,板端缝的增强层应有较强的适应基层变形的能力,可采用以下方法处理:
①卷材增强层。采用卷材作增强层应采取空铺的方法。可采用200~300mm宽、1.2mm厚的高分子卷材或3mm厚改性沥青卷材单边点粘在板端处,或用压敏型粘结剂,然后铺贴大面积防水层。
②涂膜增强层。采用加胎体的防水涂料作增强层,涂料可采用与大面积防水层相容的高分子涂料或聚合物改性沥青涂料。其作法是,在板端缝处200—300mm宽范围先涂刷隔离层150~250mm(如石灰水、石蜡或压敏型抗裂胶),干燥后逐层涂刷防水涂料,铺设胎体,一般一布三涂或二布四涂,然后再施工大面积防水层。
参考文献:
【1】GB 50108-2008.地下工程防水技术规范[S].
【2】张云霞,刘琳,赵荣香. 建筑物防水施工的要点[J].山西建筑, 2007,(05).【3】建筑施工手册(第四版)[M].北京:中国建筑工业出版社,2003.