潘三东风井冲积层厚度为358.48米,井筒净直径为6.5米,其冻结带井壁厚度为2米,冻结深度为415米。冻结孔布置圈直径为17米,孔数42个,开孔间距为1.271米,360米水平钻孔偏斜要求不超过2.5‰,最大孔间距不得超过3.0米。据潘集矿区施工的17万米冻结钻孔的经验,孔深超过120米发生偏斜时,用扫、扩、铲的方法难以纠过来,因此如何保证钻孔质量、减少钻孔偏斜、确保冻结壁厚度和井筒开挖安全,将关系施工的成败。为了确保潘三东风井415米深冻结孔质量,采用了戴纳钻具,实践证明,它可以在定向钻进中及时地灵活地进行纠偏,并使冲积层底部(360米水平)孔间距符合设计要求。
Pansan Dongfeng alluvial thickness of 358.48 meters, the borehole net diameter of 6.5 meters, the freezing wall thickness of 2 meters, the freezing depth of 415 meters. Frozen hole layout circle diameter of 17 meters, 42 holes, hole spacing of 1.271 meters, 360 meters horizontal hole deflection requirements of not more than 2.5 ‰, the maximum hole spacing of not more than 3.0 meters. According to Panji mining 17 million meters of frozen drilling experience, hole depth of more than 120 meters skew, with sweeping, expanding, shovel method is difficult to correct it, so how to ensure the quality of drilling, reduce drilling deflection, Ensuring frozen wall thickness and wellbore excavation safety will have a bearing on the success of the construction. In order to ensure the quality of 415 m deep frozen hole in Pansan Dongfeng well, Dana drill is adopted. It has been proved that it can be flexibly corrected in time and directionally, and the hole spacing at the bottom of the alluvial layer (360m horizontal) conforms to Design requirements.