一、概况石太线白羊墅车辆段转向架车间工程,地处低山丘陵坡脚处,整个车间位于山坡填平范围,填土高从1.0m到15m不等,原地形崎岖起伏,拆除村落未经清除,在古窑洞与残垣断壁之上动土填筑,施工时又未经分层碾压,因此造成虚实不一,均匀性很差。该厂房原设计为
I. Overview Shihtai Bai Shek car segment bogie workshop project, is located at the foot of hilly slopes, the entire workshop is located in the range of slopes, filling height ranging from 1.0m to 15m, the original terrain rugged, demolition The village has not been cleared and the earth has been filled and filled up on the ancient cave and the ruins of the ruins. When the village was under construction, the gravel was rolled without layering, resulting in different actual conditions and poor uniformity. The plant was originally designed as