在水电站的建设中,过去和现在都出现过不少机组在运行时因轴向水推力过大,超过了设计值,导致推力瓦温高、瓦面磨损、烧瓦、限负荷运行等。其原因是:上冠向泄水锥内排水减压径向斜孔,起不到排水减压的作用,反而有泵的增压作用;转轮直径大、转速高、旋转水头高,向泄水锥也不能排水减压;
In the construction of hydropower stations, there have been many units in the past and now because of axial thrust in the operation is too large, exceeding the design value, resulting in high thrust and temperature, tile surface wear and tear, burning tile, load-limiting operation. The reason is: the crown to the drainage cone within the drainage decompression radial oblique hole, can not play the role of drainage decompression, but the pump supercharger effect; runner diameter, high speed, high head rotation to the vent Water cone can not drain decompression;