近年来,大庆油田每年需要建成35kV 变电所10余座。为了缩短野外施工周期,加强工厂预制化,1985年大庆与辽西开关厂协作,设计了一套适应大庆外围油田施工特点的全装配化变电所,全部设备由该厂制造并现场安装。1985年10月全装配化变电所在龙一联投产运行,均达到设计规定的技术指标,受到好评。1986年,石油部在胶县召开的“三化设计三化施工”会议上该项设计被评为三化设计优秀项目。
In recent years, Daqing Oilfield needs to build more than 10 substations of 35kV each year. In order to shorten the construction period in the field and strengthen the prefabrication of the factory, Daqing cooperated with the Liaoxi Switchgear Factory in 1985 and designed a fully assembled substation suitable for the construction features of Daqing’s peripheral oil fields. All the equipment was manufactured by the plant and installed on site. In October 1985, the entire assembly-transformation substation was put into production and operation, and both reached the design specifications and were well received. In 1986, the Ministry of Petroleum held the design of the “Three Constructions Three Constructions” conference held in Jiaoxian County. The design was rated as an excellent project of Sanhua Design.